Permit: T11CM02956
Permit Details
Apply Date:
09/13/2011
Applicant:
N/A
Description:
TI: KITCHEN
Architects:
- FUENTEVILLA, MIGUEL RAUL
Contractors:
- CUTSHAW YEAGER CONSTRUCTION LLC
Permit Reviews
Permit Number - T11CM02956
Permit Status: C of o
Permit Description: TI: KITCHEN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/13/2011 | PLANS OK TO SUBMIT - COMM | 09/13/2011 | COMPLETED |
09/13/2011 | COMMERCIAL - TI | 10/11/2011 | COMPLETED |
10/11/2011 | RESUBMITTAL | 11/03/2011 | COMPLETED |
11/03/2011 | RESUBMITTAL | 11/07/2011 | COMPLETED |
11/07/2011 | RESUBMITTAL | 11/16/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02956
Permit Status: C of o
Permit Description: TI: KITCHEN
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/13/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02956
Permit Description: TI: KITCHEN
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/02/2011 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
12/02/2011 | PLUMBING - PROGRESS | LHANLY | Approved | |
12/02/2011 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
12/02/2011 | PLUMBING - PRE SLAB | LHANLY | Approved | |
12/02/2011 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
12/02/2011 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
12/02/2011 | BUILDING ABOVE CEILING | LHANLY | Approved | |
12/02/2011 | FRAMING | LHANLY | Approved | |
12/06/2011 | MECHANICAL - PROGRESS | LHANLY | Approved | |
12/06/2011 | MECHANICAL - HOODS | LHANLY | Approved | HOOD, DUCT, FAN ALL INSTALLED OK. NEED TO RUN POWER TO FAN AND PERFORM CONTAINMENT TEST. |
12/07/2011 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
12/07/2011 | ELECTRIC - PROGRESS | LHANLY | Approved | OK TO CLEAR ECO |
12/07/2011 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
12/07/2011 | BUILDING - PROGRESS | LHANLY | Approved | |
12/08/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER L. HANLY |
01/04/2012 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
01/04/2012 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
01/04/2012 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
01/04/2012 | SHEET ROCK NAILING | LHANLY | Approved | |
01/06/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
01/10/2012 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
01/18/2012 | FIRE - FINAL | WMOTTO | Approved | |
01/18/2012 | FIRE - KITCHEN EXH HOOD FINAL | WMOTTO | Approved | |
03/27/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
03/27/2012 | PLUMBING - FINAL | LHANLY | Approved | |
03/27/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
03/27/2012 | BUILDING - FINAL | LHANLY | Approved |