Permit: T11CM02500
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
1950 W SPEEDWAY BL 02
Address NEW:
1950 W SPEEDWAY BL 02
Apply Date:
08/09/2011
Applicant:
N/A
Description:
NEW APARTMENT COMPLEX:BLDG # 2
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
- LA FRONTERA CENTER *APA* PEPPER VINER
Permit Reviews
Permit Number - T11CM02500
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX:BLDG # 2
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2012 | RESUBMITTAL | 02/28/2012 | COMPLETED |
| 02/28/2012 | RESUBMITTAL | 03/08/2012 | COMPLETED |
| 03/15/2013 | REVISION - - 2ND | 03/15/2013 | COMPLETED |
| 08/09/2011 | PLANS OK TO SUBMIT - COMM | 08/23/2011 | COMPLETED |
| 08/29/2011 | COMMERCIAL - NEW | 09/29/2011 | COMPLETED |
| 09/26/2012 | REVISION - - 1ST | 10/04/2012 | COMPLETED |
| 10/04/2012 | REVISION - - 1ST | 10/04/2012 | COMPLETED |
| 10/26/2011 | RESUBMITTAL | 11/30/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02500
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX:BLDG # 2
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/09/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02500
Permit Description: NEW APARTMENT COMPLEX:BLDG # 2
Total Completed Inspections - 45
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2012 | BUILDING - FINAL | GBONILLA | Approved | RWRD hold will be released from Wastewater letter required |
| 02/20/2013 | ELECTRIC - UFER | MPUGH | Approved | IVRS - Inspection :* |
| 02/27/2013 | PLUMBING - ROUGH, SOIL | MPUGH | Approved | IVRS - Inspection :* |
| 03/13/2013 | PLUMBING - PRE SLAB | MPUGH | Approved | IVRS - Inspection :* |
| 03/13/2013 | ELECTRIC - UNDERGROUND | MPUGH | Approved | IVRS - Inspection :* |
| 04/26/2013 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 04/26/2013 | EXCAVATION/LAYOUT REBAR & ZON | RMYERS | Approved | |
| 04/26/2013 | EXT METAL CLIPS/EXT SHEATHING | RMYERS | Approved | |
| 05/08/2013 | ELECTRIC - PROGRESS | MPUGH | Approved | IVRS - Inspection :$ |
| 05/08/2013 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 05/08/2013 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 05/08/2013 | U VALUE FOR WINDOW | MPUGH | Approved | IVRS - Inspection :* |
| 05/17/2013 | FRAMING | MPUGH | Approved | IVRS - Inspection :* |
| 05/17/2013 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 05/17/2013 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 05/17/2013 | MECHANICAL - UNDERGROUND | MPUGH | Approved | IVRS - Inspection :* |
| 06/03/2013 | SHEET ROCK NAILING | MPUGH | Approved | IVRS - Inspection :* |
| 06/03/2013 | FIREWALL/FIREBARRIER/FIRESTOP | MPUGH | Approved | IVRS - Inspection :* |
| 06/03/2013 | STUCCO MESH | MPUGH | Approved | IVRS - Inspection :* |
| 06/03/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 08/01/2013 | FIRE SPKLR - UG, PIPING, HYDRO | wmotto | Approved | |
| 08/14/2013 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 08/15/2013 | TEP CLEARANCE - AM | MPUGH | Approved | ECO 2104, 2105, 2204, 2205, 2106, 2107, 2206, 2207 |
| 08/26/2013 | NPPO - FINAL | MRUSSO | Approved | |
| 08/26/2013 | SIGN - FINAL | MRUSSO | Approved | |
| 08/27/2013 | FIRE SPKLR - UG PIPING FLUSH | wmotto | Approved | |
| 08/28/2013 | RIGHT OF WAY - FINAL | tw | Approved | |
| 08/28/2013 | BUILDING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
| 08/29/2013 | ELECTRIC - OUTDOOR LIGHTING | MPUGH | Approved | |
| 08/29/2013 | SITE - SEWER | MPUGH | Approved | |
| 08/29/2013 | ROOF NAILING | MPUGH | Approved | |
| 08/29/2013 | REINFORCED MASONRY PRE-GROUT | MPUGH | Approved | |
| 08/29/2013 | BUILDING PRE-SLAB | MPUGH | Approved | |
| 08/29/2013 | STEM WALL/RETAINING WALL | MPUGH | Approved | |
| 08/29/2013 | MECHANICAL - FINAL | MPUGH | Approved | |
| 08/29/2013 | PLUMBING - INTERMEDIATE | MPUGH | Approved | |
| 08/29/2013 | PLUMBING - YARD WTR LINE/TEST | MPUGH | Approved | |
| 08/29/2013 | PLUMBING - PROGRESS | MPUGH | Approved | |
| 08/29/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 08/29/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/29/2013 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 08/29/2013 | FIRE - HYDRANTS | wmotto | Approved | |
| 08/29/2013 | FIRE SPKLR - OH PIPING & HYDRO | wmotto | Approved | |
| 08/29/2013 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 09/13/2013 | FIRE - FINAL | wmotto | Approved |