Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
1950 W SPEEDWAY BL 01
Apply Date:
08/09/2011
Applicant:
N/A
Description:
NEW APARTMENT COMPLEX: BLDG # 1
Architects:
  • CARHUFF, PHILIP ANDREW
Contractors:
  • CANYON BUILDING AND DESIGN LLC *APA*
  • LA FRONTERA CENTER *APA* PEPPER VINER

Permit Reviews

Permit Number - T11CM02499
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX: BLDG # 1
Start Date Submittal Complete Date Status  
02/14/2012 RESUBMITTAL 02/28/2012 COMPLETED Review Details
02/28/2012 RESUBMITTAL 03/08/2012 COMPLETED Review Details
03/15/2013 REVISION - - 2ND 03/15/2013 COMPLETED Review Details
04/16/2013 REVISION - - 3RD 04/24/2013 COMPLETED Review Details
08/09/2011 PLANS OK TO SUBMIT - COMM 08/23/2011 COMPLETED Review Details
08/29/2011 COMMERCIAL - NEW 09/29/2011 COMPLETED Review Details
09/26/2012 REVISION - - 1ST 10/04/2012 COMPLETED Review Details
10/04/2012 REVISION - - 1ST 10/04/2012 COMPLETED Review Details
10/26/2011 RESUBMITTAL 11/30/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM02499
Permit Status: C of o
Permit Description: NEW APARTMENT COMPLEX: BLDG # 1
Total Outstanding Activity Conditions - 1
Date Name
08/09/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM02499
Permit Description: NEW APARTMENT COMPLEX: BLDG # 1
Total Completed Inspections - 47
Date Description Inspector Results Comments
10/01/2012 BUILDING - FINAL GBONILLA Approved RWRD hold will be released from Wastewater letter required
02/20/2013 ELECTRIC - UFER MPUGH Approved IVRS - Inspection :*
03/07/2013 BUILDING PRE-SLAB MPUGH Approved IVRS - Inspection :*
04/09/2013 ROOF NAILING RMYERS Approved
04/26/2013 EXT METAL CLIPS/EXT SHEATHING RMYERS Approved
04/26/2013 EXCAVATION/LAYOUT REBAR & ZON RMYERS Approved
04/26/2013 ELECTRIC - ABOVE CEILING RMYERS Approved
04/26/2013 ELECTRIC - INTERMEDIATE RMYERS Approved
05/01/2013 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
05/14/2013 MECHANICAL - INTERMEDIATE MPUGH Approved IVRS - Inspection :*
05/14/2013 MECHANICAL - UNDERGROUND MPUGH Approved IVRS - Inspection :*
05/14/2013 U VALUE FOR WINDOW MPUGH Approved IVRS - Inspection :*
05/14/2013 FRAMING MPUGH Approved IVRS - Inspection :*
05/24/2013 BUILDING ABOVE CEILING RMYERS Approved
05/24/2013 SHEET ROCK NAILING RMYERS Approved
05/24/2013 FIREWALL/FIREBARRIER/FIRESTOP RMYERS Approved
06/03/2013 STUCCO MESH MPUGH Approved IVRS - Inspection :*
08/14/2013 ELECTRIC - FINAL MPUGH Approved IVRS - Inspection :*
08/15/2013 TEP CLEARANCE - AM MPUGH Approved ECO ELEV PANEL, HOUSE PANEL, 1203, 1202, 1201, 1103, 1102, 1101
08/23/2013 FIRE SPKLR - UG, PIPING, HYDRO wmotto Approved
08/23/2013 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
08/26/2013 NPPO - FINAL MRUSSO Approved
08/26/2013 SIGN - FINAL MRUSSO Approved
08/28/2013 RIGHT OF WAY - FINAL tw Approved
08/29/2013 BUILDING - PROGRESS MPUGH Approved
08/29/2013 BUILDING - TEMP POWER FOR TEST MPUGH Approved
08/29/2013 REINFORCED MASONRY PRE-GROUT MPUGH Approved
08/29/2013 STEM WALL/RETAINING WALL MPUGH Approved
08/29/2013 MECHANICAL - FINAL MPUGH Approved
08/29/2013 MECHANICAL - ABOVE CEILING MPUGH Approved
08/29/2013 PLUMBING - PROGRESS MPUGH Approved
08/29/2013 SITE - SEWER MPUGH Approved
08/29/2013 PLUMBING - INTERMEDIATE MPUGH Approved
08/29/2013 PLUMBING - PRE SLAB MPUGH Approved
08/29/2013 PLUMBING - ROUGH, SOIL MPUGH Approved
08/29/2013 ELECTRIC - OUTDOOR LIGHTING MPUGH Approved
08/29/2013 ELECTRIC - PROGRESS MPUGH Approved
08/29/2013 ELECTRIC - UNDERGROUND MPUGH Approved
08/29/2013 FIRE SPKLR - FINAL wmotto Approved
08/29/2013 FIRE - FINAL wmotto Approved
08/29/2013 FIRE SPKLR - OH PIPING & HYDRO wmotto Approved
08/29/2013 FIRE - LANE SIGNS wmotto Approved
08/29/2013 FIRE - HYDRANTS wmotto Approved
08/29/2013 FIRE SPKLR - UG PIPING FLUSH wmotto Approved
08/29/2013 PLUMBING - FINAL MPUGH Approved IVRS - Inspection :*
09/10/2013 ENGINEERING - FINAL DROBERTS Approved 1) PROVIDE REVISED DRAWINGS SHOWING ALL CHANGES MADE TO THIS SITE ALONG WITH A STAMPED APPROVED CERTIFICATION LETTER FROM THE ENGINEER OF RECORD. 2) CLEAN ALL CONCRETE RESIDUE FROM THIS SITE AS NOTED DURING THE WALK THROUGH ON THIS DATE ALONG THE NORTH AND WEST SIDE OF THE BUILDINGS.
09/10/2013 LANDSCAPE - FINAL DROBERTS Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW
001_T1.0.TIF CONSTRPLANS VIEW
002_C0.1.TIF CONSTRPLANS VIEW
003_C0.2.TIF CONSTRPLANS VIEW
004_C1.1.TIF CONSTRPLANS VIEW
005_C1.2.TIF CONSTRPLANS VIEW
006_C1.3.TIF CONSTRPLANS VIEW
007_C1.4.TIF CONSTRPLANS VIEW
008_C2.1.TIF CONSTRPLANS VIEW
009_C2.2.TIF CONSTRPLANS VIEW
010_C3.0.TIF CONSTRPLANS VIEW
011_C3.1.TIF CONSTRPLANS VIEW
012_SHEET 1 OF 1 .TIF CONSTRPLANS VIEW
013_C4.1.TIF CONSTRPLANS VIEW
014_L1.0.TIF CONSTRPLANS VIEW
015_L2.0.TIF CONSTRPLANS VIEW
016_L3.0.TIF CONSTRPLANS VIEW
017_N1.0.TIF CONSTRPLANS VIEW
018_N2.0.TIF CONSTRPLANS VIEW
019_A1.0.TIF CONSTRPLANS VIEW
020_A1.1.TIF CONSTRPLANS VIEW
021_A1.2.TIF CONSTRPLANS VIEW
022_A1.3.TIF CONSTRPLANS VIEW
023_A1.4.TIF CONSTRPLANS VIEW
024_A2.0.TIF CONSTRPLANS VIEW
025_A2.1.TIF CONSTRPLANS VIEW
026_A2.2.TIF CONSTRPLANS VIEW
027_A2.3.TIF CONSTRPLANS VIEW
028_A2.4.TIF CONSTRPLANS VIEW
029_A2.5.TIF CONSTRPLANS VIEW
030_A2.6.TIF CONSTRPLANS VIEW
031_A3.0.TIF CONSTRPLANS VIEW
032_A4.0.TIF CONSTRPLANS VIEW
033_A5.0.TIF CONSTRPLANS VIEW
034_A5.1.TIF CONSTRPLANS VIEW
035_A6.0.TIF CONSTRPLANS VIEW
036_A7.0.TIF CONSTRPLANS VIEW
037_A7.1.TIF CONSTRPLANS VIEW
038_A8.0.TIF CONSTRPLANS VIEW
039_A9.0.TIF CONSTRPLANS VIEW
040_A10.0.TIF CONSTRPLANS VIEW
041_S1.1.TIF CONSTRPLANS VIEW
042_S1.2.TIF CONSTRPLANS VIEW
043_S1.3.TIF CONSTRPLANS VIEW
044_S1.4.TIF CONSTRPLANS VIEW
045_S1.5.TIF CONSTRPLANS VIEW
046_S2.1.TIF CONSTRPLANS VIEW
047_S2.2.TIF CONSTRPLANS VIEW
048_S3.1.TIF CONSTRPLANS VIEW
049_S3.2.TIF CONSTRPLANS VIEW
050_S4.1.TIF CONSTRPLANS VIEW
051_S5.1.TIF CONSTRPLANS VIEW
052_S5.2.TIF CONSTRPLANS VIEW
053_S6.1.TIF CONSTRPLANS VIEW
054_S6.2.TIF CONSTRPLANS VIEW
055_M0.1.TIF CONSTRPLANS VIEW
056_M1.1.TIF CONSTRPLANS VIEW
057_M1.2.TIF CONSTRPLANS VIEW
058_M2.1.TIF CONSTRPLANS VIEW
059_P0.1.TIF CONSTRPLANS VIEW
060_P1.1.TIF CONSTRPLANS VIEW
061_P1.2.TIF CONSTRPLANS VIEW
062_P2.1.TIF CONSTRPLANS VIEW
063_P3.1.TIF CONSTRPLANS VIEW
064_E0.1.TIF CONSTRPLANS VIEW
065_E0.2.TIF CONSTRPLANS VIEW
066_E1.1.TIF CONSTRPLANS VIEW
067_E2.1.TIF CONSTRPLANS VIEW
068_E2.2.TIF CONSTRPLANS VIEW
069_E2.3.TIF CONSTRPLANS VIEW
070_E2.4.TIF CONSTRPLANS VIEW
071_E3.1.TIF CONSTRPLANS VIEW
072_E3.2.TIF CONSTRPLANS VIEW
009_A9.0.TIF CONSTRPLANS VIEW