Permit: T11CM01896
Permit Details
Apply Date:
06/16/2011
Applicant:
MARIO CHAVEZ
Description:
TI: OFFICE
Architects:
- FRANKS, MICHAEL WILLIAM
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T11CM01896
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/11/2012 | RESUBMITTAL | 01/26/2012 | COMPLETED |
01/11/2012 | REVISION - - 1ST | 01/26/2012 | COMPLETED |
01/26/2012 | REVISION - - 1ST | 01/31/2012 | COMPLETED |
06/16/2011 | PLANS OK TO SUBMIT - COMM | 06/16/2011 | COMPLETED |
06/16/2011 | COMMERCIAL - TI | 07/15/2011 | COMPLETED |
07/18/2011 | RESUBMITTAL | 08/10/2011 | COMPLETED |
08/10/2011 | RESUBMITTAL | 01/11/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM01896
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/16/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM01896
Permit Description: TI: OFFICE
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/13/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
01/13/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
01/13/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
01/13/2012 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
01/13/2012 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
01/13/2012 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* |
01/20/2012 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
01/20/2012 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
01/26/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
01/26/2012 | FIRE - FINAL | DSIWARSKI | Approved | |
01/31/2012 | BUILDING - FINAL | LHANLY | Approved | |
01/31/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
01/31/2012 | PLUMBING - FINAL | LHANLY | Approved | |
01/31/2012 | PLUMBING - PROGRESS | LHANLY | Approved | |
01/31/2012 | PLUMBING - GAS PRESS TEST FNL | LHANLY | Approved | |
01/31/2012 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
01/31/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
01/31/2012 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
01/31/2012 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
01/31/2012 | PLUMBING - GAS PRESS TEST FNL | LHANLY | Approved | |
01/31/2012 | PLUMBING - GAS PRESSURE TEST | LHANLY | Approved | |
01/31/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
01/31/2012 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
01/31/2012 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
01/31/2012 | BUILDING - FINAL | LHANLY | Approved | OK TO FINAL WHEN REVISION FEES PAID |