Permit: T11CM00869
Permit Details
Apply Date:
03/23/2011
Applicant:
N/A
Description:
APARTMENT BLDG 5 STORY ( BLDG 2)
Contractors:
- CONSTRUCTION ENTERPRISES INC
Permit Reviews
Permit Number - T11CM00869
Permit Status: C of o
Permit Description: APARTMENT BLDG 5 STORY ( BLDG 2)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/23/2011 | PLANS OK TO SUBMIT - COMM | 03/23/2011 | COMPLETED |
03/23/2011 | COMMERCIAL - NEW | 04/29/2011 | COMPLETED |
04/29/2011 | RESUBMITTAL - TI ALL | 05/23/2011 | COMPLETED |
05/23/2011 | RESUBMITTAL | 06/23/2011 | COMPLETED |
09/01/2011 | REVISION - - 1ST | 09/01/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00869
Permit Status: C of o
Permit Description: APARTMENT BLDG 5 STORY ( BLDG 2)
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/23/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00869
Permit Description: APARTMENT BLDG 5 STORY ( BLDG 2)
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2011 | PLUMBING - ROOF DRAINS | LHANLY | Approved | 12" DRAIN UNDER BLD 2 SECTION 1 OK |
11/10/2011 | FIRE SPKLR - UG, PIPING, HYDRO | DSIWARSKI | Approved | 200 PSI Stand Pipe test on South building approved. |
11/28/2011 | PLUMBING - PROGRESS | LHANLY | Approved | |
12/12/2011 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | MASONRY FIRE-WALL TO 12' |
12/12/2011 | BUILDING - PROGRESS | LHANLY | Approved | MASONRY FIRE-WALL TO 12' |
12/17/2011 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | SATURDAY INSPECTION. FEE ADDED TO PERMIT. |
12/28/2011 | PLUMBING - PRE SLAB | LHANLY | Approved | |
12/28/2011 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
12/28/2011 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | ELEVATOR AND FIRE WALL |
12/28/2011 | BUILDING PRE-SLAB | LHANLY | Approved | |
12/28/2011 | STEM WALL/RETAINING WALL | LHANLY | Approved | |
12/28/2011 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
04/12/2012 | STUCCO MESH | LHANLY | Approved | |
04/12/2012 | ROOF NAILING | LHANLY | Approved | |
04/12/2012 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
04/30/2012 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
05/15/2012 | MECHANICAL - PROGRESS | LHANLY | Approved | |
05/15/2012 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
05/15/2012 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
05/15/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
05/15/2012 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
05/15/2012 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
05/15/2012 | U VALUE FOR WINDOW | LHANLY | Approved | |
05/15/2012 | BUILDING ABOVE CEILING | LHANLY | Approved | |
05/15/2012 | FRAMING | LHANLY | Approved | |
06/22/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
07/17/2012 | FIRE - FINAL | WMOTTO | Approved | |
07/17/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | |
07/17/2012 | FIRE - LANE SIGNS | WMOTTO | Approved | |
07/17/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
07/17/2012 | PLUMBING - FINAL | LHANLY | Approved | |
07/17/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
07/17/2012 | ELECTRIC - PROGRESS | LHANLY | Approved | |
07/17/2012 | BUILDING - FINAL | LHANLY | Approved |