Permit: T11CM00707
Permit Details
Apply Date:
03/07/2011
Applicant:
N/A
Description:
ADDITION: 43.7 KVA ROOF MOUNTED SOLAR PV SYSTEM
Contractors:
- BLUE OAK ENERGY INC
Permit Reviews
Permit Number - T11CM00707
Permit Status: Final
Permit Description: ADDITION: 43.7 KVA ROOF MOUNTED SOLAR PV SYSTEM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/07/2011 | PLANS OK TO SUBMIT - COMM | 03/07/2011 | COMPLETED |
03/07/2011 | COMMERCIAL - TI | 04/22/2011 | COMPLETED |
04/22/2011 | RESUBMITTAL | 05/24/2011 | COMPLETED |
05/24/2011 | REVISION - - 1ST | 05/24/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00707
Permit Status: Final
Permit Description: ADDITION: 43.7 KVA ROOF MOUNTED SOLAR PV SYSTEM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/07/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11CM00707
Permit Description: ADDITION: 43.7 KVA ROOF MOUNTED SOLAR PV SYSTEM
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/10/2011 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
05/10/2011 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
05/10/2011 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
06/01/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) SOAP TEST FINAL CONNECTION |
06/01/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
06/01/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
06/03/2011 | FIRE - FINAL | WMOTTO | Approved | |
06/03/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | |
06/03/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
06/03/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
06/03/2011 | BUILDING - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
06/06/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR "PHOTOVOLTAIC SYSTEM" PER R. HOLLANDER |
06/06/2011 | PERMIT FINALED | JWEATHER | Approved |