Permit: T11CM00526
Permit Details
Apply Date:
02/22/2011
Applicant:
N/A
Description:
TI:OFFICE
Architects:
- VOGEL, BENJAMIN ARMANDO
Contractors:
- COSEC LAND DEVELOPMENT L L C
Permit Reviews
Permit Number - T11CM00526
Permit Status: C of o
Permit Description: TI:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/22/2011 | PLANS OK TO SUBMIT - COMM | 02/22/2011 | COMPLETED |
02/22/2011 | COMMERCIAL - TI | 03/11/2011 | COMPLETED |
03/23/2011 | RESUBMITTAL - TI ALL | 03/23/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00526
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/22/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00526
Permit Description: TI:OFFICE
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/24/2011 | BUILDING - PROGRESS | LHANLY | Approved | |
03/24/2011 | FRAMING | LHANLY | Approved | |
03/24/2011 | FRAMING | LHANLY | Approved | |
03/24/2011 | ELECTRIC - UFER | LHANLY | Approved | |
03/24/2011 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
03/24/2011 | PLUMBING - PROGRESS | LHANLY | Approved | |
03/24/2011 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
03/24/2011 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
03/24/2011 | PLUMBING - PRE SLAB | LHANLY | Approved | |
03/24/2011 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
04/05/2011 | SHEET ROCK NAILING | LHANLY | Approved | |
05/13/2011 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
05/13/2011 | PLUMBING - FINAL | LHANLY | Approved | |
05/13/2011 | U VALUE FOR WINDOW | LHANLY | Approved | |
05/13/2011 | BUILDING ABOVE CEILING | LHANLY | Approved | |
05/13/2011 | ELECTRIC - PROGRESS | LHANLY | Approved | |
05/13/2011 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
05/17/2011 | ELECTRIC - FINAL | LHANLY | Approved | |
05/17/2011 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
05/24/2011 | MECHANICAL - FINAL | LHANLY | Approved | |
05/24/2011 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | |
06/14/2011 | FIRE - FINAL | WMOTTO | Approved | |
06/15/2011 | FIRE - ALARM FINAL | WMOTTO | Approved | See T11BU00475 |
06/15/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | See T11BU00475 |
06/15/2011 | BUILDING - FINAL | LHANLY | Approved | |
06/15/2011 | SIGN - FINAL | LHANLY | Approved |