Permit Details

Status:
Final
Type:
COMMERCIAL ADDITION
Address NEW:
4975 S LIBERTY AV
Apply Date:
01/18/2011
Applicant:
N/A
Description:
ADDT: RAMADA
Architects:
  • ROWE, STEPHANIE ALICE
Contractors:
  • TOFEL CONSTRUCTION

Permit Reviews

Permit Number - T11CM00124
Permit Status: Final
Permit Description: ADDT: RAMADA
Start Date Submittal Complete Date Status  
01/18/2011 COMMERCIAL - BLDG/FIRE/ZONING/ENG 01/20/2011 COMPLETED Review Details
01/20/2011 COMMERCIAL - BLDG/FIRE/ZONING/ENG 01/21/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM00124
Permit Status: Final
Permit Description: ADDT: RAMADA
Total Outstanding Activity Conditions - 1
Date Name
01/18/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T11CM00124
Permit Description: ADDT: RAMADA
Total Completed Inspections - 19
Date Description Inspector Results Comments
02/17/2011 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
02/17/2011 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
02/24/2011 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
03/04/2011 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
1) NEED TO SEE CIRCUITS TIE IN COLUMN
03/04/2011 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
03/04/2011 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
03/04/2011 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
03/09/2011 FRAMING MHENSON Approved IVRS - Inspection :*
03/09/2011 EXCAVATION/LAYOUT REBAR & ZON MHENSON Approved IVRS - Inspection :*
03/15/2011 RIGHT OF WAY - FINAL MCASTRO Approved
03/15/2011 NPPO - FINAL LMakus Approved
03/15/2011 LANDSCAPE - FINAL LMakus Approved
03/15/2011 ENGINEERING - FINAL LMakus Approved
03/15/2011 FIRE - FINAL CSCHULTZ Approved
03/15/2011 SIGN - FINAL JYBARRA Approved
03/22/2011 BUILDING - FINAL MHENSON Approved
03/22/2011 ELECTRIC - FINAL DSANTACR Approved
03/22/2011 PLUMBING - FINAL RRICH Approved
03/22/2011 PLUMBING - PROGRESS RRICH Approved