Permit: T10CM03295
Permit Details
Apply Date:
11/24/2010
Applicant:
N/A
Description:
ADDITION:BEDROOM:BATHROOM
Architects:
- SZADKOWSKI, MIREK EDWARD
Contractors:
- TUCSON CONSTRUCTION GROUP
Permit Reviews
Permit Number - T10CM03295
Permit Status: Final
Permit Description: ADDITION:BEDROOM:BATHROOM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/01/2011 | REVISION - - 1ST | 02/01/2011 | COMPLETED |
03/04/2011 | REVISION - - 2ND | 03/04/2011 | COMPLETED |
11/24/2010 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 11/24/2010 | COMPLETED |
11/24/2010 | RESIDENTIAL - BLDG/WWM | 12/27/2010 | COMPLETED |
12/27/2010 | RESUBMITTAL | 01/05/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM03295
Permit Status: Final
Permit Description: ADDITION:BEDROOM:BATHROOM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/24/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM03295
Permit Description: ADDITION:BEDROOM:BATHROOM
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/04/2011 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
02/04/2011 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
02/04/2011 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
02/04/2011 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
02/24/2011 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
03/02/2011 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | IVRS - Inspection :* |
03/03/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER D. QUINN |
03/04/2011 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
03/04/2011 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
03/09/2011 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
03/11/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
04/05/2011 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
04/05/2011 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | ZONING - FINAL | DQUINN | Approved | |
04/22/2011 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | IVRS - Inspection :* |
04/22/2011 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | IVRS - Inspection :* |
09/13/2011 | PERMIT FINALED | JWEATHER | Approved |