Permit: T10CM03267
Permit Details
Apply Date:
11/19/2010
Applicant:
N/A
Description:
TI: OFFICE AND C OF O
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T10CM03267
Permit Status: C of o
Permit Description: TI: OFFICE AND C OF O
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/19/2010 | COMMERCIAL - TI | 11/29/2010 | COMPLETED |
11/29/2010 | COMMERCIAL - TI | 11/30/2010 | COMPLETED |
12/17/2010 | REVISION - - 1ST | 12/21/2010 | COMPLETED |
12/21/2010 | REVISION - - 1ST | 12/21/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM03267
Permit Status: C of o
Permit Description: TI: OFFICE AND C OF O
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/19/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM03267
Permit Description: TI: OFFICE AND C OF O
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/06/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* 1) TEST THRU ROOF FOR SINK AND WATER COOLER (ONLY) |
12/08/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
12/13/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
12/16/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
12/17/2010 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* 1) GAS PIPE SUPPLYING UNITS 12 AND 32 ONLY ON ROOF |
12/23/2010 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
12/28/2010 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
12/29/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) WALLS AND CEILINGS IN BLDG OK |
12/29/2010 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
12/29/2010 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
12/29/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
12/29/2010 | FIRE SPKLR - FINAL | IVR USER | Approved | IVRS - RI canceled |
01/03/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
01/03/2011 | FIRE - FINAL | LTHOMAS | Approved | |
01/03/2011 | SIGN - FINAL | JYBARRA | Approved | |
01/03/2011 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
01/03/2011 | NPPO - FINAL | JFEMLING | Approved | Approved |
01/03/2011 | LANDSCAPE - FINAL | JFEMLING | Approved | Approved |
01/04/2011 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
01/04/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
01/04/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
01/05/2011 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | |
01/11/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
01/12/2011 | PLUMBING - FINAL | JBURGE | Approved | |
01/12/2011 | BUILDING - FINAL | JBURGE | Approved |