Permit: T10CM03117
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
6422 E SPEEDWAY BL #120
Address NEW:
6422 E SPEEDWAY BL #120
Apply Date:
11/05/2010
Applicant:
N/A
Description:
TI and CofO: OFFICE
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO
Permit Reviews
Permit Number - T10CM03117
Permit Status: C of o
Permit Description: TI and CofO: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/05/2010 | COMMERCIAL - TI | 04/05/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM03117
Permit Status: C of o
Permit Description: TI and CofO: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/05/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM03117
Permit Description: TI and CofO: OFFICE
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/22/2010 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/23/2010 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 11/30/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
| 12/02/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 12/03/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 12/03/2010 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 12/03/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 12/15/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
| 12/28/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/28/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
| 12/28/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/28/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 02/04/2011 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
| 02/14/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | RECN CLEARED PER R. MORENO-SENT OVER TO TEP ON 02/07/11 IN THE AM |
| 02/16/2011 | NPPO - FINAL | DROBERTS | Approved | |
| 02/16/2011 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 02/16/2011 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 02/16/2011 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 02/16/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 02/16/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 02/16/2011 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 02/17/2011 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 03/31/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/04/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 04/04/2011 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 04/04/2011 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | IVRS - Inspection :* |
| 04/04/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |