Permit: T10CM02829
Permit Details
Apply Date:
10/12/2010
Applicant:
N/A
Description:
ADD; GARAGE
Permit Reviews
Permit Number - T10CM02829
Permit Status: Final
Permit Description: ADD; GARAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/03/2011 | REVISION - - 1ST | 02/03/2011 | COMPLETED |
| 10/12/2010 | RESIDENTIAL BLDG/ZONING-WALKTHRU | 10/12/2010 | COMPLETED |
| 10/12/2010 | RESIDENTIAL BLDG/WWM | 11/10/2010 | COMPLETED |
| 11/16/2010 | RESUBMITTAL | 11/30/2010 | COMPLETED |
| 11/30/2010 | RESUBMITTAL | 12/06/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM02829
Permit Status: Final
Permit Description: ADD; GARAGE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/12/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM02829
Permit Description: ADD; GARAGE
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2011 | EXCAVATION/LAYOUT REBAR & ZON | DWALKER | Approved | IVRS - Inspection :* |
| 01/24/2011 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | IVRS - Inspection :* |
| 01/25/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER D. QUINN |
| 01/28/2011 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | IVRS - Inspection :* |
| 02/09/2011 | ROOF NAILING | DWALKER | Approved | IVRS - Inspection :* |
| 02/11/2011 | PLUMBING - ROUGH, SOIL | DWALKER | Approved | IVRS - Inspection :* |
| 03/01/2011 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 04/08/2011 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
| 06/28/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 09/15/2011 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
| 09/15/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 09/15/2011 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 09/15/2011 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 09/15/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 09/28/2011 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 09/29/2011 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 09/29/2011 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 10/03/2011 | STEM WALL/RETAINING WALL | DQUINN | Approved | IVRS - Inspection :* |