Permit: T10CM02501
Permit Details
Apply Date:
09/08/2010
Applicant:
N/A
Description:
TI:PHYSICAL THERAPY
Architects:
- EGLIN, EVAN SAR
Contractors:
- BOCK COMMERCIAL CONSTRUCTION L L C
Permit Reviews
Permit Number - T10CM02501
Permit Status: C of o
Permit Description: TI:PHYSICAL THERAPY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/08/2010 | COMMERCIAL TI | 09/27/2010 | COMPLETED |
09/10/2010 | RESUBMITTAL | 09/27/2010 | COMPLETED |
09/27/2010 | RESUBMITTAL | 11/23/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM02501
Permit Status: C of o
Permit Description: TI:PHYSICAL THERAPY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/08/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM02501
Permit Description: TI:PHYSICAL THERAPY
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/08/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
10/08/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
10/18/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) CONDENSATE DRAIN OK 2) SUPPLY AND EXHAUST IN RESTROOMS OK 3) DRYER VENT OK |
10/18/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
10/22/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
10/22/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
11/15/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
11/15/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
11/15/2010 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
11/15/2010 | ELECTRIC - TEMPORARY SERVICE | RJIROUDE | Approved | IVRS - Inspection :* |
11/15/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
11/15/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
11/15/2010 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
11/15/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/15/2010 | FIRE - FINAL | LTHOMAS | Approved | |
11/15/2010 | NPPO - FINAL | DROBERTS | Approved | |
11/15/2010 | LANDSCAPE - FINAL | DROBERTS | Approved | |
11/16/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
11/16/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
11/16/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "METER #1" PER R. JIROUDEK |
11/17/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
11/22/2010 | ENGINEERING - FINAL | DROBERTS | Approved | |
11/23/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
11/23/2010 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
11/23/2010 | GREEN BUILDING - GENERAL | GDABBS | Approved | IVRS - Inspection :* |
11/23/2010 | MECHANICAL - FINAL | GDABBS | Approved | IVRS - Inspection :* |
11/23/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
11/23/2010 | CERTIFICATE OF OCCUPANCY | GDABBS | Approved | IVRS - Inspection :* |