Permit: T10CM02274
Permit Details
Apply Date:
08/17/2010
Applicant:
N/A
Description:
TOWNHOUSE:AFST000210 T10-M0008
Contractors:
- A F STERLING HOME BUILDERS LTD
Permit Reviews
Permit Number - T10CM02274
Permit Status: C of o
Permit Description: TOWNHOUSE:AFST000210 T10-M0008
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/17/2010 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/18/2010 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM02274
Permit Description: TOWNHOUSE:AFST000210 T10-M0008
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/10/2010 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* |
09/10/2010 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
09/10/2010 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
09/29/2010 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* 1) STUB UP OK |
09/29/2010 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
09/29/2010 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
09/29/2010 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
01/27/2011 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | IVRS - Inspection :* |
02/22/2011 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
02/22/2011 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
04/06/2011 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
04/19/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
05/05/2011 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | IVRS - Inspection :* |
05/05/2011 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
05/06/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER D. QUINN |
08/03/2011 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
08/03/2011 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
08/03/2011 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
08/03/2011 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
08/03/2011 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | IVRS - Inspection :* |