Permit: T10CM01598
Permit Details
Apply Date:
06/14/2010
Applicant:
N/A
Description:
NEW OFFICE:SHOP
Architects:
- STICKLEY DESIGN GROUP
Contractors:
- P AND H CONTRACTING INC ,
Permit Reviews
Permit Number - T10CM01598
Permit Status: C of o
Permit Description: NEW OFFICE:SHOP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/14/2011 | RESUBMITTAL | 07/12/2011 | COMPLETED |
06/14/2010 | PLANS OK TO SUBMIT - COMM | 06/14/2010 | COMPLETED |
06/14/2010 | COMMERCIAL NEW | 07/19/2010 | COMPLETED |
08/16/2010 | RESUBMITTAL | 04/14/2011 | COMPLETED |
10/12/2012 | REVISION - - 2ND | 10/12/2012 | COMPLETED |
10/12/2012 | REVISION - - 2ND | 10/23/2012 | COMPLETED |
12/14/2011 | REVISION - - 1ST | 12/14/2011 | COMPLETED |
12/14/2011 | REVISION - - 1ST | 12/29/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01598
Permit Status: C of o
Permit Description: NEW OFFICE:SHOP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/14/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01598
Permit Description: NEW OFFICE:SHOP
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/27/2012 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection :* |
03/07/2012 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
03/07/2012 | ELECTRIC - UFER | AQUIROZ | Approved | IVRS - Inspection :* |
03/07/2012 | PLUMBING - PRE SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
05/02/2012 | ELECTRIC - UNDERGROUND | AQUIROZ | Approved | IVRS - Inspection :* |
06/27/2012 | TEP CLEARANCE - AM | MPUGH | Approved | |
08/09/2012 | FRAMING | MPUGH | Approved | IVRS - Inspection :* |
09/04/2012 | PLUMBING - PROGRESS | MPUGH | Approved | IVRS - Inspection :* |
09/04/2012 | PLUMBING - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
09/04/2012 | PLUMBING - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
09/04/2012 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
09/04/2012 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
09/06/2012 | BUILDING PRE-SLAB | MPUGH | Approved | IVRS - Inspection :* |
09/11/2012 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | 1ST FLOOR |
09/11/2012 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | 1ST FLOOR |
09/11/2012 | SHEET ROCK NAILING | MPUGH | Approved | 1ST FLOOR |
05/23/2013 | EXCAVATION/LAYOUT REBAR & ZON | MPUGH | Approved | IVRS - Inspection :* |
05/23/2013 | BUILDING ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
03/05/2014 | PLUMBING - GAS PRESS TEST FNL | MPUGH | Approved | IVRS - Inspection :* |
03/05/2014 | PLUMBING - GAS PRESSURE TEST | MPUGH | Approved | IVRS - Inspection :* |
07/10/2014 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
07/10/2014 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
07/10/2014 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
07/10/2014 | OUTDOOR LIGHTING FINAL | MPUGH | Approved | IVRS - Inspection :* |
07/10/2014 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |
07/11/2014 | NPPO - FINAL | MRUSSO | Approved | |
07/11/2014 | SIGN - FINAL | MRUSSO | Approved | |
07/11/2014 | LANDSCAPE - FINAL | MRUSSO | Approved | |
10/08/2014 | FIRE - FINAL | CBASALDUA | Approved | |
10/29/2014 | BUILDING - PROGRESS | MPUGH | Approved | |
10/29/2014 | EXT METAL CLIPS/EXT SHEATHING | MPUGH | Approved | |
10/29/2014 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
10/30/2014 | ENGINEERING - FINAL | MRUSSO | Approved | |
11/14/2014 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved | IVRS - Inspection :* |
11/18/2014 | ELECTRIC - OUTDOOR LIGHTING | AQUIROZ | Approved | IVRS - Inspection :* |
12/22/2014 | ZONING - FINAL | DGR | Approved | |
12/22/2014 | FIRE SPKLR - FINAL | CBASALDUA | Approved | 1. No sprinkler system in this building. |