Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T10CM01190
Permit Details
Apply Date:
04/29/2010
Applicant:
N/A
Description:
REMODEL and CofO: APARTMENTS 1-8
Architects:
- PAULUS, ROBERT FRANCIS
Contractors:
- COFFEE BUILDERS INC
Permit Reviews
Permit Number - T10CM01190
Permit Status: C of o
Permit Description: REMODEL and CofO: APARTMENTS 1-8
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2010 | PLANS OK TO SUBMIT - COMM | 05/27/2010 | COMPLETED |
05/27/2010 | COMMERCIAL TI | 06/25/2010 | COMPLETED |
07/02/2010 | RESUBMITTAL | 07/09/2010 | COMPLETED |
07/09/2010 | RESUBMITTAL | 07/21/2010 | COMPLETED |
10/14/2010 | REVISION - - 1ST | 10/14/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01190
Permit Status: C of o
Permit Description: REMODEL and CofO: APARTMENTS 1-8
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/29/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01190
Permit Description: REMODEL and CofO: APARTMENTS 1-8
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/23/2010 | PLUMBING - PRE SLAB | LHANLY | Approved | |
08/23/2010 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
10/28/2010 | U VALUE FOR WINDOW | LHANLY | Approved | |
10/28/2010 | FRAMING | LHANLY | Approved | |
10/28/2010 | ROOF NAILING | LHANLY | Approved | |
10/28/2010 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
10/28/2010 | BUILDING PRE-SLAB | LHANLY | Approved | |
10/28/2010 | ELECTRIC - INTERMEDIATE | LHANLY | Approved | |
10/28/2010 | MECHANICAL - INTERMEDIATE | LHANLY | Approved | |
10/28/2010 | PLUMBING - INTERMEDIATE | LHANLY | Approved | |
11/17/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | CEC CLEARED FOR UNITS #1,2,3,4,5,6,7 & 8 PER L. HANLY |
11/17/2010 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
11/17/2010 | ELECTRIC - UFER | LHANLY | Approved | |
11/17/2010 | ELECTRIC - CABLE DROP | LHANLY | Approved | |
11/22/2010 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
12/03/2010 | BUILDING - PROGRESS | LHANLY | Approved | |
12/03/2010 | SHEET ROCK NAILING | LHANLY | Approved | |
12/03/2010 | FIREWALL/FIREBARRIER/FIRESTOP | LHANLY | Approved | |
12/03/2010 | BUILDING ABOVE CEILING | LHANLY | Approved | |
12/03/2010 | BUILDING ABOVE CEILING | LHANLY | Approved | |
12/03/2010 | ELECTRIC - PROGRESS | LHANLY | Approved | |
12/03/2010 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | |
12/03/2010 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
12/03/2010 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | |
12/03/2010 | PLUMBING - PROGRESS | LHANLY | Approved | |
12/03/2010 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
12/03/2010 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
12/03/2010 | PLUMBING - BACK WATER VALVE | LHANLY | Approved | |
12/21/2010 | CERTIFICATE OF OCCUPANCY | LHANLY | Approved | NEED TO GET FIRE SPRINKLER FINAL BEFORE CofO CAN BE SIGNED OFF. |
12/21/2010 | BUILDING - FINAL | LHANLY | Approved | |
12/21/2010 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
12/21/2010 | ELECTRIC - FINAL | LHANLY | Approved | |
12/21/2010 | MECHANICAL - FINAL | LHANLY | Approved | |
12/21/2010 | PLUMBING - FINAL | LHANLY | Approved | |
12/23/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved |