Permit: T10CM01144
Permit Details
Apply Date:
04/27/2010
Applicant:
N/A
Description:
NEW SFR
Contractors:
- MEADERS CONSTRUCTION L L C
Permit Reviews
Permit Number - T10CM01144
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/27/2010 | PLANS OK TO SUBMIT - RES | 04/27/2010 | COMPLETED |
| 04/27/2010 | RESIDENTIAL BLDG/WWM | 06/02/2010 | COMPLETED |
| 06/02/2010 | RESUBMITTAL | 06/14/2010 | COMPLETED |
| 06/14/2010 | RESUBMITTAL | 06/21/2010 | COMPLETED |
| 06/23/2010 | REVISION - - 1ST | 06/23/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01144
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/27/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01144
Permit Description: NEW SFR
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2010 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/02/2010 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 07/02/2010 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
| 07/02/2010 | PLUMBING - PRE SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 07/02/2010 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 07/02/2010 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 07/02/2010 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 07/06/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER D. QUINN |
| 07/27/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 07/27/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 08/11/2010 | PLUMBING - ABOVE CEILING | EDURAZO | Approved | IVRS - Inspection :* |
| 08/11/2010 | ELECTRIC - ABOVE CEILING | EDURAZO | Approved | IVRS - Inspection :* |
| 08/11/2010 | MECHANICAL - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 08/11/2010 | PLUMBING - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 08/11/2010 | ELECTRIC - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 08/11/2010 | BUILDING ABOVE CEILING | EDURAZO | Approved | IVRS - Inspection :* |
| 08/17/2010 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO EXTERIOR |
| 08/18/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* APPROVED OK TO TAPE THROUGHOUT |
| 09/13/2010 | ELECTRIC - PROGRESS | DQUINN | Approved | IVRS - Inspection :* |
| 10/12/2010 | MECHANICAL - FINAL | DWALKER | Approved | |
| 10/12/2010 | PLUMBING - FINAL | DWALKER | Approved | |
| 10/12/2010 | ELECTRIC - FINAL | DWALKER | Approved | |
| 10/12/2010 | BUILDING - FINAL | DWALKER | Approved | |
| 10/14/2010 | PERMIT FINALED | JWEATHER | Approved |