Permit Number - T10CM00727
Permit Status: C of o
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/23/2010 | COMMERCIAL TI | 04/06/2010 | COMPLETED |
| 04/06/2010 | RESUBMITTAL | 05/13/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00727
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/23/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00727
Permit Description: TI: OFFICE
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 06/04/2010 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 06/21/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 06/21/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) FOR FINAL PROVIDE ACCESS TO ROOF 2) AIR BALANCE REPORT 3) BE SURE CONDENSATE IS TERMINATED TO AN APPROVED LOCATION |
| 06/21/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
| 06/22/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 06/24/2010 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/24/2010 | FIRE - ALARM FINAL | LThomas | Approved | Not applicable 6/24/10 |
| 06/24/2010 | FIRE - FINAL | LThomas | Approved | Approved 6/24/10 |
| 06/24/2010 | FIRE SPKLR - FINAL | LThomas | Approved | Approved 6/24/10 |
| 06/24/2010 | RIGHT OF WAY - FINAL | PWhiddon | Approved | |
| 06/24/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 07/16/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 07/21/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 07/30/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/02/2010 | ROOF NAILING | GDABBS | Approved | |
| 08/02/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* 1) PHASE 2 & 3 COMPLETE |
| 08/03/2010 | PERMIT FINALED | JWEATHER | Approved |