Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
02/25/2010
Applicant:
N/A
Description:
TI: RESTAURANT EL CON MALL
Architects:
  • PATRICK J VENTURA
Contractors:
  • HAWORTH CORPORATION , THE

Permit Reviews

Permit Number - T10CM00475
Permit Status: C of o
Permit Description: TI: RESTAURANT EL CON MALL
Start Date Submittal Complete Date Status  
02/25/2010 PLANS OK TO SUBMIT - COMM 02/25/2010 COMPLETED Review Details
02/25/2010 COMMERCIAL TI 05/25/2010 COMPLETED Review Details
03/22/2010 RESUBMITTAL 04/07/2010 COMPLETED Review Details
04/07/2010 RESUBMITTAL 04/08/2010 COMPLETED Review Details
04/08/2010 RESUBMITTAL 06/14/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10CM00475
Permit Status: C of o
Permit Description: TI: RESTAURANT EL CON MALL
Total Outstanding Activity Conditions - 1
Date Name
02/25/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T10CM00475
Permit Description: TI: RESTAURANT EL CON MALL
Total Completed Inspections - 36
Date Description Inspector Results Comments
06/17/2010 ELECTRIC - UNDERGROUND RJIROUDE Approved IVRS - Inspection :*
06/18/2010 PLUMBING - PRE SLAB RMYERS Approved IVRS - Inspection :*
1) CORRECTIONS MADE OK
2) WATER TEST ONE RISER TO TEN FEET OK
3) OK TO BACKFILL
06/18/2010 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
06/29/2010 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection :*
07/01/2010 FRAMING JBURGE Approved IVRS - Inspection :*
1) OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES
07/08/2010 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO TAPE THROUGHOUT
07/20/2010 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved
07/20/2010 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved IVRS - Inspection :*
07/22/2010 PLUMBING - GAS PRESS TEST FNL RRICH Approved IVRS - Inspection :*
07/28/2010 RIGHT OF WAY - FINAL MOTERO Approved
07/28/2010 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
1) FINISH INSULATING HOT AND ? PIPING
07/28/2010 LANDSCAPE - FINAL MRUSSO Approved
07/29/2010 FIRE SPKLR - FINAL LTHOMAS Approved
07/30/2010 MECHANICAL - HOODS JMILITEL Approved IVRS - Inspection :*
07/30/2010 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
07/30/2010 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
07/30/2010 NPPO - FINAL MCARREON Approved
07/30/2010 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*
07/30/2010 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
07/30/2010 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
07/30/2010 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
07/30/2010 ROOF NAILING JBURGE Approved IVRS - Inspection :*
08/02/2010 ELECTRIC - PROGRESS RMORENO Approved
08/02/2010 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*
1) PLUMBING FINAL OK
2) AFTER HOURS INSPECTION-PAID $150.00 BY CHECK #02848
08/02/2010 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
08/02/2010 ENGINEERING - FINAL JFEMLING Approved Site work complete, approved
08/02/2010 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
08/02/2010 ELECTRIC - ABOVE CEILING RMORENO Approved IVRS - Inspection :*
08/02/2010 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
08/03/2010 FIRE - FINAL NRAMIREZ Approved
08/03/2010 FIRE - KITCHEN EXH HOOD FINAL DRamirez Approved Approved 8/3/10
08/03/2010 FIRE - FINAL DRamirez Approved Approved 8/3/10
08/04/2010 MECHANICAL - FINAL JMILITEL Approved
08/04/2010 HEALTH DEPT - FINAL 724-7908 NRAMIREZ Approved
08/04/2010 CERTIFICATE OF OCCUPANCY GDABBS Approved
08/04/2010 BUILDING - FINAL GDABBS Approved