Permit: T10CM00310
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
9121 E CAMINO ABRIL
Address NEW:
9121 E CAMINO ABRIL
Apply Date:
02/10/2010
Applicant:
N/A
Description:
TI:
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T10CM00310
Permit Status: C of o
Permit Description: TI:
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2010 | COMMERCIAL TI | 02/19/2010 | COMPLETED |
| 02/19/2010 | RESUBMITTAL | 04/16/2010 | COMPLETED |
| 04/16/2010 | REVISION - - 1ST | 04/29/2010 | COMPLETED |
| 09/21/2010 | REVISION - - 2ND | 09/21/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00310
Permit Status: C of o
Permit Description: TI:
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/10/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00310
Permit Description: TI:
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2010 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/18/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/31/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 04/13/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 04/13/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) PROVIDE BACKING AROUND CEILING BOXES PRIOR TO SHEETROCK |
| 04/13/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) CALL IN 03075 FOR CLOSET FLANGE |
| 04/13/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 04/15/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 04/30/2010 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 05/20/2010 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* 1) CLOSET FLANGE OK |
| 09/16/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 09/16/2010 | NPPO - FINAL | DROBERTS | Approved | |
| 09/16/2010 | ENGINEERING - FINAL | DROBERTS | Approved | A TEMPORARY C OF O IS APPROVABLE AT THIS TIME, cHRIS GENTER HAS BEEN INFORMED OF THISISSUES ON THIS DATE. A FINAL WILL NOT BE GIVEN UNTIL THE PLANS HAVE BEEN CHANGED TO MEET THE EXISTING FIELD CONDITIONS OR TILL THE FIELD CONDITIONS MEET THE CURRENT PLANS. I HAVE ASKED THEDEVELOPER TO DISCUSS THE CHANGES THAT HAVE BEEN MADE WITH THE ENGINEEERING AND ZONING REVIEWERS, AND THAT ALL CHANGES BE NOTED ON AN APPROVED AS-BUILT DRAWINGS. THESE DRAWING WILL BE NEEDED TO PERFORM THE FINAL INSPECTION. THE SITE CHANGES INCLUDED BUT ARE NOT LIMITED TO THE FOLLOWING AREAS: 1) ASPHALTIC CONCRETE IN LOCATIONS NOT SHOWN ON THE APPROVED PLANS. 2) EXTRUDED CURB EITHER IN LOCATIONS NOT SHOWN ON THE APPROVED PLANS OR DELETED TOTALLT FROM THE APPROVED PLASN. 3) TREE'S, SHRUBS, AND PLANTS NOT LAYED OUT IN GENERAL PER THE APPROVED PLAN, SOME OF THE PLANTS APPEAR TO BE SMALLER THAT WHAT THE PLANS HAVE SPECIFIED. ALL AREAS WILL BE CHECKED FULLY TO ENSURE THAT IT IS PER EITHER THE APPROVED GRADING PLAN OR PER THE NEW RIVISION PLAN FOR THIS SITE. I HAVE ASKED THAT THE DEVELOPER SUBMIT ALL CHANGES TO THIS SITE AND ALL OTHER SITES PRIOR TO CALLING IN FOR THE FINAL INSPECTIONS FOR THE COMBO PERMITS. THIS SHOULD ENSURE THAT THERE WILL BE NO DELAYS IN THE ISSUEING OF C OF O'S IF ALL MODIFICATIONS ARE APPROVED BEFOREHAND. |
| 09/16/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 09/16/2010 | FIRE - FINAL | CSCHULTZ | Approved | |
| 09/20/2010 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/20/2010 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/20/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/20/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/20/2010 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/20/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/22/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 09/22/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 09/22/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 09/24/2010 | BUILDING - PROGRESS | GDABBS | Approved | |
| 09/27/2010 | CERTIFICATE OF OCCUPANCY | GDABBS | Approved | IVRS - Inspection :* 1) NO ACCESS-DOOR LOCKED |
| 09/20/2011 | LANDSCAPE - FINAL | DROBERTS | Approved |