Permit: T10CM00121
Permit Details
Apply Date:
01/19/2010
Applicant:
N/A
Description:
TI: RETAIL
Architects:
- EGLIN, EVAN SAR
Contractors:
- BOCK COMMERCIAL CONSTRUCTION L L C
Permit Reviews
Permit Number - T10CM00121
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2010 | COMMERCIAL TI | 02/03/2010 | COMPLETED |
02/03/2010 | OTHER | 02/05/2010 | COMPLETED |
02/26/2010 | REVISION - - 1ST | 03/03/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00121
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/19/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00121
Permit Description: TI: RETAIL
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/10/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) WATER TEST FROM EXISTING THRU CLEANOUT HEIGHT OK |
02/10/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
02/19/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
02/22/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
02/25/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1) PERIMETER TO BE ON SITE |
03/03/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) CLOSET FLANGE OK FOR VINYL OR VCT ONLY |
03/03/2010 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
03/08/2010 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
03/09/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #175 PER R. JIROUDEK |
03/10/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
03/10/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
03/10/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
03/10/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
03/10/2010 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
03/10/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
03/10/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
03/10/2010 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
03/10/2010 | FIRE - FINAL | DRamirez | Approved | Approved 3/10/10 |
03/10/2010 | NPPO - FINAL | ACONNOR | Approved | N/A |
03/10/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
03/11/2010 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
03/11/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
03/11/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
03/11/2010 | SIGN - FINAL | JYBARRA | Approved | |
03/11/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
03/16/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
03/17/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
03/17/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
03/17/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
03/18/2010 | FIRE SPKLR - FINAL | DRamirez | Approved | PER C OF O FIRE |