Permit: T10BU00315
Permit Details
Apply Date:
02/19/2010
Applicant:
RAMZI GEORGES
Description:
AZ STATE VET HOME SWPP
Contractors:
- HAYDON BUILDING CORP
Permit Reviews
Permit Number - T10BU00315
Permit Status: Expired
Permit Description: AZ STATE VET HOME SWPP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/19/2010 | GRADING | 03/11/2010 | COMPLETED |
03/11/2010 | RESUBMITTAL - SWPPP | 03/24/2010 | COMPLETED |
03/24/2010 | SWPPP | 04/08/2010 | COMPLETED |
04/08/2010 | RESUBMITTAL - SWPPP | 04/14/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10BU00315
Permit Status: Expired
Permit Description: AZ STATE VET HOME SWPP
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
02/19/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
04/12/2010 | The following 14 conditions apply to permit T10OT00396 & T10BU00315: 1) Any outstanding utility issues must be resolved through the applicable utility companies. Contractor is responsible to coordinate all work near utility lines with the proper utilities prior to any site construction. 2) Call for Pre-construction meeting. Discuss during Pre-con or contact PDSD Engineering Inspector to confirm which drainage inspections may be needed. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at Planning & Development Services Department (PDSD), or contact PDSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html 3) This Drainage Plan and SWPPP are only for onsite drainage improvement construction associated with the Arizona State Veterans Home project as shown on the approved SWPPP and drainage plans (T10OT00396 & T10BU00315). See also Final Drainage Statement (April 2010) sealed 4/7/10 by Ramzi Georges, P.E. 4) A copy of stamped approved drainage plans, permits, and reports shall be kept at site at all times, until final drainage approval. 5) Interim erosion and sediment controls shall be maintained per approved SWPPP plans at downstream areas of disturbance limits. Prior to Final Approval all temporary controls shall be removed and permanent controls shall be placed. 6) Stabilized entrances shall be maintained at all active access entrances. Use of water trucks or other dust controls shall be utilized, and construction entrances shall be maintained to minimize sedimentation, dust issues, and tracking. 7) Storage or placement of construction material, vehicle staging / stockpile area, and/or designated concrete washout locations shall not be located within or near any basins, or water harvesting areas. 8) During construction activities, traffic control plans may be required if there is a safety hazard potential from construction activities conflicting with public traffic. Onsite traffic control plans shall minimize traffic hazard conditions between public access to buildings, and construction vehicles & activities. 9) Any revisions to Drainage Plan must be reviewed by PDSD Engineering Engineer and may include discussion, details, or a revised drainage report or plans. Call PDSD Engineering at 791-5550 to discuss any revisions. 10) For inspection purposes, post City of Tucson's "AZPDES - Posting Requirements" green sheet, or the NOI at construction entrance of site, at beginning of construction activities, and maintain this posted document throughout project construction. 11) All Operators shall be identified and have separate certification statements. Assure these certifications are available on-site. 12) Operator shall report to ADEQ any noncompliance (including spills) which may endanger human health or the environment. Operator shall orally notify office listed below within 24 hours: (a) Arizona Department of Environmental Quality 1110 W. Washington, 5th floor (5515B-1) Phoenix, AZ 85007 Office: 602-771-4466; Fax 602-771-4505 13) Permitee shall notify PDSD when operation is ready for final drainage inspection. Final drainage approval shall not be given until all work, including installation of all drainage improvements and their permanent protective devices, and all erosion control measures have been completed in accordance with approved drainage plan and permit, and all conditions of permit are completed. 14) As-builts are required to be submitted under activity number T10OT00396 to PDSD permit clerks. They will be reviewed and then if acceptable, a copy will be provided to PDSD Engineering Inspector for final drainage inspections. For Permit Project Closure documentation, submit: 2 copies of as-builts, letter of completion for basin and other drainage improvements. As-builts shall include: constructed elevations for basin bleed pipe adjacent to utilities, and finished grades for drainage systems. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T10BU00315
Permite Description: AZ STATE VET HOME SWPP
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/01/2011 | GRADING - INTERMEDIATE | N/A | Continued | WORKING ON CURBING ON NORTH SIDE OF BUILDING. |
04/05/2011 | GRADING - TIER REV | N/A | Correction Required | EOR to submit detail regarding revised basin design for review. At this time a bleed pipe is required, and NO other design has been approved. See also conditions for T10OT00396. |
11/15/2010 | STORMWATER FOLLOW-UP INSP | N/A | Approved | COT RESPONSIBLE FOR STORMWATER INSPECTIONS ONLY. CONTACT RON OWSLY (602-296-1496) FOR SITE QUESTIONS. NO CONCERNS AT THIS TIME. |
Completed Inspections
Permit Status: Expired
Permit Number: T10BU00315
Permit Description: AZ STATE VET HOME SWPP
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/12/2010 | ENGINEERING PRE-CONSTRUCTION | MCARREON | Approved | ENGINEERING PRE-CON--SITE SUPER RON OWSLY 602-296-1496. CITY MONITORING SWWPP. INSTALLATION OF PERIMETER CONTROLS INSTALLED 5/12/10. PROJECT DURATION 18 MO. |
10/22/2010 | STORMWATER INSTALL OF CONTROLS | MCARREON | Approved | SPOKE WITH SITE SUPER. CONST. CONTINUES. CONTROLS WILL BE REMOVED AS JOB IS COMPLETED. INLETS CONTINUE TO BE PROTECTED. |