Permit: T10BU00136
Permit Details
Apply Date:
01/26/2010
Applicant:
JASON KUKLINSKI
Description:
GRADING PERMIT
Contractors:
- ANDERSON CONSTRUCTION CORP , M
Permit Reviews
Permit Number - T10BU00136
Permit Status: Final
Permit Description: GRADING PERMIT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/26/2010 | GRADING | 02/05/2010 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T10BU00136
Permit Status: Final
Permit Description: GRADING PERMIT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/26/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10BU00136
Permit Description: GRADING PERMIT
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2010 | GRADING - TIER REV | MRUSSO | Approved | MET W/ SUPERINTENDENT. CONSTRUCTION PROJECT IS A SMALL PARK <1 AC. SOME LANDSCAPING INVOLED, CONSTRUCTION OF 18" SEAT WALL, AND ADDING TO FLAGPOLE FOOTING. DG WILL BE INSTALLED AND SOD WILL BE LAID ON SLOPE, KEEP EXISTING DRAINAGE DIRECTION OF SURFACE FLOW. SWEEP UP ANY TRACKING FROM TRUCK/CONSTRUCTION TRAFFIC, PROVIDE LATEST GRADING PLAN FOR FINAL GRADING INSPECTION. LATEST REVISION IS DATED 3/4/10 |
| 03/11/2010 | GRADING - INTERMEDIATE | MRUSSO | Approved | MET W/ SUPERINTENDENT. CONSTRUCTION PROJECT IS A SMALL PARK <1 AC. SOME LANDSCAPING INVOLED, CONSTRUCTION OF 18" SEAT WALL, AND ADDING TO FLAGPOLE FOOTING. DG WILL BE INSTALLED AND SOD WILL BE LAID ON SLOPE, KEEP EXISTING DRAINAGE DIRECTION OF SURFACE FLOW. SWEEP UP ANY TRACKING FROM TRUCK/CONSTRUCTION TRAFFIC, PROVIDE LATEST GRADING PLAN FOR FINAL GRADING INSPECTION. |
| 03/11/2010 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | MET W/ SUPERINTENDENT. CONSTRUCTION PROJECT IS A SMALL PARK <1 AC. SOME LANDSCAPING INVOLED, CONSTRUCTION OF 18" SEAT WALL, AND ADDING TO FLAGPOLE FOOTING. DG WILL BE INSTALLED AND SOD WILL BE LAID ON SLOPE, KEEP EXISTING DRAINAGE DIRECTION OF SURFACE FLOW. SWEEP UP ANY TRACKING FROM TRUCK/CONSTRUCTION TRAFFIC, PROVIDE LATEST GRADING PLAN FOR FINAL GRADING INSPECTION. |
| 05/11/2010 | LANDSCAPE INSPECTION | MRUSSO | Approved | |
| 05/11/2010 | GRADING - FINAL | MRUSSO | Approved | |
| 05/11/2010 | GRADING - CHECK FOR ACTIVITY | MRUSSO | Approved | |
| 08/23/2010 | PERMIT FINALED | KMEDINA | Approved | |
| 06/12/2019 | GRADING - REBAR | RLEDONNE | Approved |