Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Apply Date:
01/13/2010
Applicant:
COSTCO GASOLINE
Description:
FUEL TANKS
Contractors:
  • JACKSON DEAN CONSTRUCTION

Permit Reviews

Permit Number - T10BU00039
Permit Status: Final
Permit Description: FUEL TANKS
Start Date Submittal Complete Date Status  
01/13/2010 TANKS 02/17/2010 COMPLETED Review Details
03/05/2010 TANKS 10/14/2010 COMPLETED Review Details
12/10/2010 TANKS 01/03/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10BU00039
Permit Status: Final
Permit Description: FUEL TANKS
Total Outstanding Activity Conditions - 1
Date Name
01/13/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T10BU00039
Permit Description: FUEL TANKS
Total Completed Inspections - 11
Date Description Inspector Results Comments
12/12/2010 FUEL TANK TIGHTNESS AND HOLE CFUNKE Approved 3- 30,000 gallon fuel tanks installed. 1- 1500 gal additive tank installed. All doublewall fiberglas, brine filled
01/25/2011 FUEL PIPING INSP. & PRESS TEST CFUNKE Approved Piping approved
04/08/2011 ELECTRIC - PROGRESS DSANTACR Approved IVRS - Inspection :*
04/08/2011 ELECTRIC - TEMPORARY SERVICE DSANTACR Approved IVRS - Inspection :*
04/08/2011 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
04/08/2011 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
04/08/2011 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
04/08/2011 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
04/12/2011 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
04/13/2011 FUEL TANK FINAL 791-4502 BCORRALE Approved Approved 04/12 @ 1300 hrs.
09/07/2011 PERMIT FINALED JWEATHER Approved