Permit: T09PL00304
Permit Details
Apply Date:
02/19/2009
Applicant:
CRYSTAL COOLING & HEATING *T
Description:
REPLACE: GAS LINE
Contractors:
- CRYSTAL COOLING & HEATING *T
Permit Reviews
Permit Number - T09PL00304
Permit Status: Final
Permit Description: REPLACE: GAS LINE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/19/2009 | PLUMBING | 02/19/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09PL00304
Permit Status: Final
Permit Description: REPLACE: GAS LINE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/19/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09PL00304
Permit Description: REPLACE: GAS LINE
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2009 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1. PRESSURE TEST OK 2. CONTRACTOR HAS REMOVED GAS FIRED WATER HEATER AND CAPPED OFF PIPE ALONG EXTERIOR WALL 3. ROOFTOP UNIT ONLY APPLIANCE 4. CONTRACTOR TO INSTALL SEDIMENT TRAP AT ROOF TOP UNIT OK FOR GAS UCC LEFT AT METER SW GAS @ 889-1888 |
| 03/03/2009 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
| 03/04/2009 | PERMIT FINALED | BFLORES | Approved |