Permit: T09EL01407
Permit Details
Apply Date:
06/05/2009
Applicant:
JOHN CICHON
Description:
TEMP POWER SERVICE
Contractors:
- FOUR LEAF CONSTRUCTION INC
Permit Reviews
Permit Number - T09EL01407
Permit Status: Final
Permit Description: TEMP POWER SERVICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/05/2009 | ELECTRICAL | 06/05/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09EL01407
Permit Status: Final
Permit Description: TEMP POWER SERVICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/05/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09EL01407
Permit Description: TEMP POWER SERVICE
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 07/02/2009 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 07/02/2009 | ELECTRIC - TEMPORARY POLE | DSANTACR | Approved | IVRS - Inspection :* |
| 07/02/2009 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 07/02/2009 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 07/06/2009 | PERMIT FINALED | JWEATHER | Approved | |
| 07/06/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER D. SANTACRUZ |