Permit: T09CM03127
Permit Details
Apply Date:
11/30/2009
Applicant:
N/A
Description:
NEW SFR
Permit Reviews
Permit Number - T09CM03127
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/27/2010 | REVISION - - 1ST | 01/27/2010 | COMPLETED |
| 12/16/2009 | PLANS OK TO SUBMIT - RES | 12/16/2009 | COMPLETED |
| 12/31/2009 | POST 3RD PARTY REVIEW | 01/05/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM03127
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/30/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM03127
Permit Description: NEW SFR
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2010 | PLUMBING - ROUGH, SOIL | EDURAZO | Approved | IVRS - Inspection :* |
| 01/13/2010 | BUILDING PRE-SLAB | EDURAZO | Approved | IVRS - Inspection :* |
| 01/13/2010 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection :* |
| 01/29/2010 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 01/29/2010 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 02/12/2010 | MECHANICAL - PROGRESS | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/12/2010 | U VALUE FOR WINDOW | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/12/2010 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/12/2010 | U VALUE FOR WINDOW | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/12/2010 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
| 02/19/2010 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | PLUMBING - PROGRESS | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 02/19/2010 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
| 03/03/2010 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 03/04/2010 | ELECTRIC - TEMPORARY SERVICE | EDURAZO | Approved | |
| 03/04/2010 | ELECTRIC - CABLE DROP | EDURAZO | Approved | |
| 03/04/2010 | TEP CLEARANCE - PM | JWEATHER | Approved | ECO CLEARED PER E. DURAZO |
| 03/16/2010 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | IVRS - Inspection :* 1) IS THERE A SHARED SEWER AGREEMENT WITH THE SOUTH LOT ? |
| 03/16/2010 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection :* |
| 06/08/2010 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) POINT SOUTHSIDE SPOT LIGHTS DOWN TO 45 DEGREE OR LESS 2) INSTALL A/C AND FUSING 3) NEED BACKFLOW PREVENTER VALVES ON HOSE BIBS 4) NEED WATER HEATER FLUE |
| 09/02/2010 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* 1) COMPLY WITH PREVIOUS 2) NO ACCESS |
| 01/06/2011 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 01/06/2011 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 01/13/2011 | PERMIT FINALED | JWEATHER | Approved |