Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T09CM02771
Permit Details
Apply Date:
10/15/2009
Applicant:
N/A
Description:
REMODEL:SFR TO BED & BREAKFAST
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T09CM02771
Permit Status: C of o
Permit Description: REMODEL:SFR TO BED & BREAKFAST
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/28/2010 | RESUBMITTAL | 07/30/2010 | COMPLETED |
07/30/2010 | RESUBMITTAL | 08/04/2010 | COMPLETED |
10/15/2009 | PLANS OK TO SUBMIT - COMM | 11/05/2009 | COMPLETED |
11/05/2009 | COMMERCIAL-BLDG/FIRE/ZONING/ENG | 12/11/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02771
Permit Status: C of o
Permit Description: REMODEL:SFR TO BED & BREAKFAST
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/15/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02771
Permit Description: REMODEL:SFR TO BED & BREAKFAST
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/02/2010 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
09/08/2010 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
09/09/2010 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) 1-1" PVC IN TRENCH IN KITCHEN OK |
09/17/2010 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* 1) NORTH BEAM POCKET-OK TO GROUT PROGRESS AREA |
09/24/2010 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
10/13/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) TUB AREAS IN BATHROOMS; FIRE WALLS ABOVE DROP CEILING-OK TO SHEETROCK PROGRESS AREAS 2) ENSURE ALL PENETRATIONS IN FIRE WALLS ARE PROPERLY FIRE CAULKED |
10/14/2010 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
10/15/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* 1) OK WALLS AND CEILINGS CANNOT USE PLASTIC BOXES WITH METAL RACEWAY OR CABLE 2) ENSURE METAL RACEWAYS ARE PROPERLY GROUNDED WILL CHECK AT NEXT INSPECTION |
10/15/2010 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
10/15/2010 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
10/15/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
10/18/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK |
10/18/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
10/21/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) FIREPLACE VENT OK TO COVER |
10/25/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
11/30/2010 | PLUMBING - BACK WATER VALVE | BBENEDON | Approved | IVRS - Inspection :* |
11/30/2010 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
12/01/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* 1) SHOWER PAN OK |
12/27/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* 1) CLOSET FLANGES OK-EXCEPT AT LAST UNIT |
01/04/2011 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
01/04/2011 | FIRE - FINAL | LTHOMAS | Approved | |
01/05/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
01/05/2011 | ELECTRIC - UFER | RMORENO | Approved | |
01/05/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
01/05/2011 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
01/05/2011 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
01/06/2011 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
01/06/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
01/07/2011 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
01/07/2011 | NPPO - FINAL | MRUSSO | Approved | |
01/07/2011 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/19/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
01/19/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
01/20/2011 | LANDSCAPE - FINAL | MRUSSO | Approved |