Permit: T09CM02491
Permit Details
Apply Date:
09/15/2009
Applicant:
N/A
Description:
TI and C OF O
Contractors:
- COFFEE BUILDERS INC
Permit Reviews
Permit Number - T09CM02491
Permit Status: C of o
Permit Description: TI and C OF O
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/15/2009 | COMMERCIAL TI | 10/07/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02491
Permit Status: C of o
Permit Description: TI and C OF O
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/15/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02491
Permit Description: TI and C OF O
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/08/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
10/13/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
10/15/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT PENDING PLUMBING INTERMEDIATE |
10/15/2009 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* 1) 2 NEW DUCTS (FLEX DUCT) ADDED TO EXISTING SYSTEM |
10/15/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* 1) CEILING IN BLDG OK |
10/15/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
10/15/2009 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
10/15/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
10/15/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
10/19/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
10/19/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
10/21/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
10/22/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) GFI, EXITS, EM AND PANEL SCHEDULE OK |
10/22/2009 | PLUMBING - FINAL | RLEDONNE | Approved | |
10/26/2009 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | Approved |
10/26/2009 | FIRE - FINAL | DSIWARSKI | Approved | Approved |
10/26/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/26/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
10/26/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
10/27/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
12/07/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
12/08/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE |
12/08/2009 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/10/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
12/10/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |