Permit: T09CM02361
Permit Details
Apply Date:
09/03/2009
Applicant:
N/A
Description:
APARTMENT:COMMUNITY BUILDING
Architects:
- FROST, MARC CAHILL
Contractors:
- SELLERS AND SONS INC ,
Permit Reviews
Permit Number - T09CM02361
Permit Status: C of o
Permit Description: APARTMENT:COMMUNITY BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/12/2010 | RESUBMITTAL | 08/26/2010 | COMPLETED |
06/21/2011 | RESUBMITTAL | 07/08/2011 | COMPLETED |
07/08/2011 | RESUBMITTAL | 07/21/2011 | COMPLETED |
08/26/2010 | RESUBMITTAL | 06/21/2011 | COMPLETED |
09/09/2009 | PLANS OK TO SUBMIT - COMM | 09/22/2009 | COMPLETED |
09/22/2009 | COMMERCIAL NEW | 10/22/2009 | COMPLETED |
12/22/2009 | RESUBMITTAL | 05/11/2010 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02361
Permit Description: APARTMENT:COMMUNITY BUILDING
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/14/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
11/21/2011 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1) 2" PVC YARDWATER MAIN INSTALLED AND BLDGS OK |
11/29/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) BLDG FOOTINGS AND SLAB OK |
11/29/2011 | ELECTRIC - UFER | MHENSON | Approved | IVRS - Inspection :* |
11/29/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
12/09/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
02/24/2012 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
03/09/2012 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
03/09/2012 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
03/27/2012 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
04/04/2012 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
04/04/2012 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
04/06/2012 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
04/06/2012 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
04/09/2012 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
04/09/2012 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
04/10/2012 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
04/24/2012 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
05/25/2012 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "ACTIVITY BLDG" PER D. SANTACRUZ |
05/25/2012 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
06/08/2012 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
06/12/2012 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/12/2012 | OUTDOOR LIGHTING FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/12/2012 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
06/13/2012 | FIRE SPKLR - UG PIPING FLUSH | WMOTTO | Approved | |
06/14/2012 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
06/14/2012 | NPPO - FINAL | RLEDONNE | Approved | |
06/14/2012 | SIGN - FINAL | RLEDONNE | Approved | |
06/14/2012 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
06/29/2012 | FIRE - FINAL | WMOTTO | Approved | |
06/29/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | |
06/29/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
06/29/2012 | ENGINEERING - FINAL | RLEDONNE | Approved | |
07/02/2012 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | |
07/02/2012 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
07/02/2012 | MECHANICAL - UNDERGROUND | RCAMACHO | Approved | |
07/02/2012 | BUILDING - FINAL | RCAMACHO | Approved |