Permit: T09CM01573
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8526 E TANQUE VERDE RD 06
Address NEW:
8526 E TANQUE VERDE RD 06
Apply Date:
06/18/2009
Applicant:
N/A
Description:
NEW RESTROOM BLDG
Architects:
- COLE, BENJAMIN WILLIAM
Contractors:
- HALLMARK CUSTOM HOMES L L C
Permit Reviews
Permit Number - T09CM01573
Permit Status: C of o
Permit Description: NEW RESTROOM BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/18/2009 | PLANS OK TO SUBMIT - COMM | 06/19/2009 | COMPLETED |
| 06/19/2009 | 3RD PARTY REVIEW-COMMERCIAL | 08/04/2009 | COMPLETED |
| 08/04/2009 | POST 3RD PARTY REVIEW | 08/11/2009 | COMPLETED |
| 08/11/2009 | RESUBMITTAL | 08/18/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01573
Permit Status: C of o
Permit Description: NEW RESTROOM BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/18/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01573
Permit Description: NEW RESTROOM BLDG
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2009 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) TRENCH OK PREVIOUSLY INSPECTED |
| 09/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) CONTINOUS F1 FOOTING AS PER SCHEDULE AND DETAILS #102 AND 103-OK TO POUR FOOTING |
| 09/08/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* 1) UFER RESTROOM #4 OK |
| 09/11/2009 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* 1) OK TO GROUT |
| 09/16/2009 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 09/16/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/22/2009 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* 1) EAST AND WEST TOPPED OUT AT 8'-8"; NORTH AND SOUTH WALLS TOPPED OUT AT 8' 10"-12' 8"; ANCHOR BOLTS IN PLACE-OK TO GROUT |
| 10/13/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* 1) PENDING PLUMBING PRE-SLAB, OK TO POUR WHEN CORRECTIONS HAVE BEEN COMPLETED |
| 10/14/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 10/20/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
| 10/20/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/20/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 11/09/2009 | FIRE SPKLR - FINAL | LThomas | Approved | Approved 11/09/09 |
| 11/09/2009 | FIRE SPKLR - OH PIPING & HYDRO | LThomas | Approved | Approved 11/9/09 |
| 11/09/2009 | FIRE SPKLR - UG PIPING FLUSH | LThomas | Approved | Approved 11/9/09 |
| 11/09/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LThomas | Approved | Approved 11/9/09 |
| 11/25/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 11/25/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR SHEETROCK |
| 11/25/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) WALLS, TRANSFORMERS AND PANELS OK |
| 11/25/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 12/03/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 12/03/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 12/08/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE AND TEXTURE THROUGHOUT |
| 12/17/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 01/07/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 01/07/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) EM, LIGHTING AND POWER ALL OK |
| 01/07/2010 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 01/07/2010 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 01/14/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 01/14/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 01/19/2010 | RIGHT OF WAY - FINAL | PWhiddon | Approved | |
| 01/19/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 01/20/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 01/20/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 01/20/2010 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 01/20/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 01/20/2010 | ENGINEERING - FINAL | MRUSSO | Approved | PART OF BIGGER DEVELOPMENT, NO DETAILS SHOWN ON STORM DRAIN TIE INTO MAIN STORM DRAIN LINE. |
| 01/21/2010 | PERMIT FINALED | JWEATHER | Approved |