Permit: T09CM01065
Permit Details
Apply Date:
04/29/2009
Applicant:
N/A
Description:
TI: ORTHOPEDICS OFFICE
Contractors:
- D R I PARTNERS INC
Permit Reviews
Permit Number - T09CM01065
Permit Status: C of o
Permit Description: TI: ORTHOPEDICS OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2009 | PLANS OK TO SUBMIT - COMM | 04/29/2009 | COMPLETED |
04/29/2009 | COMMERCIAL TI | 05/08/2009 | COMPLETED |
05/19/2009 | REVISION - - 1ST | 05/19/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01065
Permit Status: C of o
Permit Description: TI: ORTHOPEDICS OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/29/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01065
Permit Description: TI: ORTHOPEDICS OFFICE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* PVC UNDERGROUND OK TO COVER CALL 03015 FOR PRE-SLAB INSPECTION |
05/19/2009 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* PLUMBING TRENCH INFILL AND DOWELING OK |
05/19/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
06/01/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
06/04/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
06/18/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
06/18/2009 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
06/18/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #120 PER R. JIROUDEK |
06/19/2009 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
06/19/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
06/19/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
06/30/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
06/30/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
06/30/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* 1) RECIEVED LETTER FROM ENGINEER FOR CHANGE TO PANEL |
06/30/2009 | NPPO - FINAL | ACONNOR | Approved | |
06/30/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
06/30/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
06/30/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
06/30/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
06/30/2009 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
06/30/2009 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
06/30/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
06/30/2009 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
07/01/2009 | PERMIT FINALED | JWEATHER | Approved | |
07/01/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | |
07/01/2009 | FIRE SPKLR - FINAL | LHARRIS | Approved | |
07/01/2009 | ROOF NAILING | GDABBS | Approved | |
07/01/2009 | FIRE - FINAL | LHARRIS | Approved |