Permit: T09CM00929
Permit Details
Apply Date:
04/21/2009
Applicant:
N/A
Description:
NEW CITY PARK
Architects:
- ROGERS, WALT
Permit Reviews
Permit Number - T09CM00929
Permit Status: Final
Permit Description: NEW CITY PARK
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/21/2009 | PLANS OK TO SUBMIT - COMM | 04/24/2009 | COMPLETED |
04/21/2009 | PLANS OK TO SUBMIT - SITE | 04/24/2009 | COMPLETED |
04/24/2009 | COMMERCIAL NEW | 05/21/2009 | COMPLETED |
04/24/2009 | SITE | 05/21/2009 | COMPLETED |
06/16/2009 | RESUBMITTAL | 07/07/2009 | COMPLETED |
06/16/2009 | RESUBMITTAL - SITE ALL | 07/07/2009 | COMPLETED |
07/07/2009 | RESUBMITTAL | 07/08/2009 | COMPLETED |
07/07/2009 | RESUBMITTAL - SITE | 07/08/2009 | COMPLETED |
12/10/2009 | REVISION - - 1ST | 12/10/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00929
Permit Status: Final
Permit Description: NEW CITY PARK
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/21/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM00929
Permit Description: NEW CITY PARK
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/11/2009 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
12/21/2009 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* 1) CMU WEST AND ANGLE N/W CORNER WALL FROM 0' TO 4' 8" ABOVE TOP OF FOOTING |
03/22/2010 | ENGINEERING - FINAL | DROBERTS | Approved | LOOKED OVER THE SITE FOR THE FULL RELEASE OF THE COMBO PERMIT. THE FOLLOWING ITEMS HAVE BEEN NOTED AND WILL BE ADDRESSED AS NOTED 1) A PLAQUARD ON THE EAST SIDE OF THE SITE HAS BEEN REMOVED BY THE PARKS AND RECS. DEPARTMENT TO CHANGE SOME INCORRECT WORDING ON THE SIGN. 2) A.D.A. LOCATED ON THE EAST SIDE OF THE CIRCULAR PATH HAS NOT BEEN INSTALLED. I CONTACT TOM KAZINSKI WITH K.A.Z. CONSTRUCTION AND THEY WILL HAVE THAT INSTALLED ON WEDNESDAY, HE WILL ADVISE ME ONCE IT HAS BEEN GLUED SO THAT I CAN VERIFY THE CORRECT INSTALLATION. 3) A MINOR CHANGE HAS BEEN NOTED ON THE STEM WALLS LOCATED ON THE NORTHSIDE OF THE PROJECT, THESE CHANGES WILL BE REFLECTED IN THE AS-BUILT DRAWINGS FOR THIS SITE. |
03/22/2010 | ENGINEERING - FINAL | MCARREON | Approved | SITE REVIEWED FOR FINALIZATION OF THE COMBO PERMIT, PLANS HAVE NOT BEEN PROVIDED ON-SITE AT THAT TIME AND WILL BE CHECKED BY DAVID ROBERTS ONCE THEY HAVE BEEN PROVIDED. |
03/22/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | |
03/22/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
03/24/2010 | PERMIT FINALED | JWEATHER | Approved |