Permit: T09CM00658
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
801 W MIRACLE MILE 08
Address NEW:
801 W MIRACLE MILE 08
Apply Date:
03/25/2009
Applicant:
N/A
Description:
TI:INTERIOR
Architects:
- MASSE, PAUL H
Contractors:
- FOUR LEAF CONSTRUCTION INC
Permit Reviews
Permit Number - T09CM00658
Permit Status: C of o
Permit Description: TI:INTERIOR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2010 | REVISION - - 1ST | 02/04/2010 | COMPLETED |
| 03/25/2009 | PLANS OK TO SUBMIT - COMM | 03/25/2009 | COMPLETED |
| 03/25/2009 | COMMERCIAL TI | 04/14/2009 | COMPLETED |
| 04/14/2009 | RESUBMITTAL | 04/28/2009 | COMPLETED |
| 05/12/2009 | RESUBMITTAL | 05/21/2009 | COMPLETED |
| 07/16/2010 | REVISION - - 2ND | 07/30/2010 | COMPLETED |
| 12/18/2009 | REVISION - - 1ST | 12/22/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00658
Permit Status: C of o
Permit Description: TI:INTERIOR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/25/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00658
Permit Description: TI:INTERIOR
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/26/2010 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/25/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 03/23/2010 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/23/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 03/26/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 05/25/2010 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 06/11/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/11/2010 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED FOR BLDG 8-UNITS #1, 2 & 1 OWNERS METER PER D. SANTACRUZ |
| 07/13/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 07/13/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 07/13/2010 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 07/13/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 07/13/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 07/13/2010 | ELECTRIC - SERVICE RELOCATION | DSANTACR | Approved | IVRS - Inspection :* |
| 07/13/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 07/13/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 07/13/2010 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 07/13/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/15/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 07/16/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 07/16/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 07/19/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 07/19/2010 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 07/19/2010 | FIRE - LANE SIGNS | LTHOMAS | Approved | |
| 07/19/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 07/21/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 07/26/2010 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/26/2010 | NPPO - FINAL | MRUSSO | Approved | |
| 07/26/2010 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 07/26/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 07/30/2010 | RIGHT OF WAY - FINAL | MOTERO | Approved |