Permit Details

Status:
Final
Type:
SINGLE FAMILY ALTERATION
Address NEW:
6206 S PARK AV #16
Apply Date:
03/24/2009
Applicant:
N/A
Description:
REPAIRS:GENERAL MH

Permit Reviews

Permit Number - T09CM00642
Permit Status: Final
Permit Description: REPAIRS:GENERAL MH
Start Date Submittal Complete Date Status  
03/24/2009 RESIDENTIAL BLDG/ZONING/ENGINE/NPPO 03/25/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09CM00642
Permit Status: Final
Permit Description: REPAIRS:GENERAL MH
Total Outstanding Activity Conditions - 1
Date Name
03/24/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T09CM00642
Permit Description: REPAIRS:GENERAL MH
Total Completed Inspections - 12
Date Description Inspector Results Comments
08/11/2009 MECHANICAL - INTERMEDIATE RCAMACHO Approved IVRS - Inspection :
See detailed listing on site.| 999*
08/11/2009 ELECTRIC - INTERMEDIATE RCAMACHO Approved IVRS - Inspection :
See detailed listing on site.| 999*
08/26/2009 U VALUE FOR WINDOW RFREIDIN Approved IVRS - Inspection :*
1) COMPLY WITH PREVIOUS INSPECTION. UNIT MUST BE CLEARED BY CC INSPECTOR PRIOR TO ANY DSD INSPECTIONS. CALL MARTIN ROMERO 349-8237 OR 791-4605
2) GAS LINE SIZE OK
3) NEED TWO POLE BREAK H.A.CR. TYPE FOR NEW A/C UNIT
4) MOVE ALL BARE CU. GROUNDS TO GROUND BUSS ALL NEUTRALS TO ISOLATED BUSS
5) ITEMS #1 CLR. FROM CC INSPECTOR
6) INSP ROB TOOK LETTER FROM ELECTRICIAN TO TURN IN TO RECORDS
09/01/2009 TEP CLEARANCE - AM JWEATHER Approved RECN CLEARED FOR #16 PER R. FREIDINGER
09/17/2009 PLUMBING - GAS PRESSURE TEST RFREIDIN Approved IVRS - Inspection :*
09/17/2009 MECHANICAL - FINAL RFREIDIN Approved IVRS - Inspection :*
09/17/2009 PLUMBING - FINAL RFREIDIN Approved IVRS - Inspection :*
09/17/2009 ELECTRIC - FINAL RFREIDIN Approved IVRS - Inspection :*
09/17/2009 BUILDING - FINAL RFREIDIN Approved IVRS - Inspection :*
02/25/2010 REINFORCED MASONRY PRE-GROUT RFREIDIN Approved PER BU FINAL
02/25/2010 BUILDING PRE-SLAB RFREIDIN Approved PER BU FINAL
02/25/2010 SHEET ROCK NAILING RFREIDIN Approved PER BU FINAL