Permit: T09CM00356
Permit Details
Apply Date:
02/17/2009
Applicant:
N/A
Description:
TI: COMMERCIAL STORAGE SUITE 100 - FIRST TENANT IN
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T09CM00356
Permit Status: Final
Permit Description: TI: COMMERCIAL STORAGE SUITE 100 - FIRST TENANT IN
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/17/2009 | COMMERCIAL TI | 02/17/2009 | COMPLETED |
02/17/2009 | COMMERCIAL TI | 02/27/2009 | COMPLETED |
02/27/2009 | RESUBMITTAL | 03/10/2009 | COMPLETED |
03/10/2009 | RESUBMITTAL | 07/17/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00356
Permit Status: Final
Permit Description: TI: COMMERCIAL STORAGE SUITE 100 - FIRST TENANT IN
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/17/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM00356
Permit Description: TI: COMMERCIAL STORAGE SUITE 100 - FIRST TENANT IN
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/19/2009 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST UNDERGROUND THRU TEST FITTING OK PIPE WRAPS OK |
03/19/2009 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
04/06/2009 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
04/10/2009 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* GREEN BOARD ALL WET LOCATIONS |
05/07/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* 1. EXHAUST DUCT CHANGE TO FLEX OK 2. DUCT SMOKE DETECTOR TEST REQUIRED FOR FINAL 3. UNIT #160 AIR BALANCE REPORT SHOWS UNITS 1-4 AS DOES #100 AND #180 REDESIGNATE ACCORDINGLY |
05/07/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CLOSET FLANGE OK |
05/07/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
06/29/2009 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED FOR #100 PER R. HOLLANDER |
07/06/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* 1) RECEIVED LETTER OF TORQUE |
07/06/2009 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
07/06/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
07/06/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
07/06/2009 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
07/07/2009 | NPPO - FINAL | ACONNOR | Approved | |
07/07/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
07/07/2009 | ENGINEERING - FINAL | MCARREON | Approved | |
07/07/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
07/07/2009 | FIRE - FINAL | LTHOMAS | Approved | |
07/07/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
07/09/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
07/09/2009 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
07/09/2009 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
07/10/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) LETTER OF COMPLETION |
07/10/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
07/10/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
07/17/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |