Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
Grading
Address NEW:
3540 W TINY BIRD CT
Apply Date:
01/22/2009
Applicant:
N/A
Description:
GRADING FOR NEW SFR
Contractors:
  • MARQUIS BUILDERS INC ,

Permit Reviews

Permit Number - T09BU00098
Permit Status: Final
Permit Description: GRADING FOR NEW SFR
Start Date Submittal Complete Date Status  
01/22/2009 PLANS OK TO SUBMIT - GRADING 01/22/2009 COMPLETED Review Details
01/22/2009 GRADING 02/23/2009 COMPLETED Review Details
03/24/2009 GRADING 04/15/2009 COMPLETED Review Details
04/24/2009 GRADING 05/12/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09BU00098
Permit Status: Final
Permit Description: GRADING FOR NEW SFR
Total Outstanding Activity Conditions - 1
Date Name
01/22/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T09BU00098
Permit Description: GRADING FOR NEW SFR
Total Completed Inspections - 10
Date Description Inspector Results Comments
06/01/2009 ENGINEERING PRE-CONSTRUCTION MCARREON Approved MET WITH MARK YARDY OF MARQUIS BUILDERS 591-5130 FOR A PRE-CON. ADDRESS SPECIAL PERMIT CONDITIONS INDICATED BY ELIZABETH. CONTRACTOR TO CALL WHEN HE BEGINS CUTS AND BEGINS WORK ON DRAINAGE SWALE.
06/17/2009 GRADING - REBAR MCARREON Approved INCORRECTLY ENTERED GRADING REBAR INSPECTION
11/18/2009 GRADING - INTERMEDIATE MCARREON Approved SPOKE WITH CONTRACTOR REGARDING TRACKOUT ON TO STARR PASS
12/04/2009 GRADING - CHECK FOR ACTIVITY MCARREON Approved WORK CONTINUES. FENCING UP AROUND ENTIRE SITE. SIDEWALK CLOSED OFF. STUCCO WORK SET TO BEGIN.
01/25/2010 STORMWATER INSTALL OF CONTROLS MCARREON Approved CHECKED FOR STORMWATER CONCERNS. PROJECT NEARING COMPLETION. AWAITING FINAL INSPECTION REQUEST.
03/02/2010 STORMWATER FINAL INSPECTION DROBERTS Approved
03/23/2010 STORMWATER FOLLOW-UP INSP DROBERTS Approved
07/14/2020 GRADING - FINAL DROBERTS Approved
07/14/2020 LANDSCAPE INSPECTION DROBERTS Approved
07/14/2020 NPPO PRE PERMIT INSPECTION DROBERTS Approved