Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
8300 E VALENCIA RD 05
Apply Date:
12/29/2008
Applicant:
N/A
Description:
NEW METAL STORAGE BLDG (BLDG 5)
Architects:
  • ARMSTRONG, TERRY
Contractors:
  • SIERRA LAND SURVEYING AND DEVELO

Permit Reviews

Permit Number - T08CM03989
Permit Status: C of o
Permit Description: NEW METAL STORAGE BLDG (BLDG 5)
Start Date Submittal Complete Date Status  
01/13/2009 POST 3RD PARTY REVIEW 01/13/2009 COMPLETED Review Details
12/29/2008 PLANS OK TO SUBMIT - COMM 12/29/2008 COMPLETED Review Details
12/29/2008 3RD PARTY REVIEW-COMMERCIAL 01/13/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM03989
Permit Status: C of o
Permit Description: NEW METAL STORAGE BLDG (BLDG 5)
Total Outstanding Activity Conditions - 1
Date Name
12/29/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM03989
Permit Description: NEW METAL STORAGE BLDG (BLDG 5)
Total Completed Inspections - 36
Date Description Inspector Results Comments
02/11/2009 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
04/21/2009 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
04/21/2009 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
04/21/2009 ELECTRIC - UFER RJIROUDE Approved IVRS - Inspection :*
04/21/2009 ELECTRIC - UFER RJIROUDE Approved IVRS - Inspection :*
04/22/2009 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
07/16/2009 ROOF NAILING GDABBS Approved IVRS - Inspection :*
07/16/2009 EXT METAL CLIPS/EXT SHEATHING GDABBS Approved IVRS - Inspection :*
09/02/2009 ELECTRIC - CABLE DROP RJIROUDE Approved IVRS - Inspection :*
1) OK 1-4" PVC FROM TEP XFMR TO BLDG
2) PLAN CALLS FOR 2-4" RACEWAYS. INSTALL PER PLANS OR REVISE PLANS
3) INSTALL WORKING RIBBON PER NEC 300.5
02/16/2010 FRAMING GDABBS Approved IVRS - Inspection :*
1) PRE-ENGINEERED BLDG FRAMING ONLY
03/04/2010 SITE - SEWER RRICH Approved IVRS - Inspection :*
03/05/2010 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
05/25/2010 ELECTRIC - TEMP POWER FOR TEST RJIROUDE Approved IVRS - Inspection :*
05/26/2010 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED FOR BLDG #5 PER R. JIROUDEK
11/01/2010 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
1) DWV AND WATER TEST OK
2) CLOSET FLANGES OK FOR CONCRETE OR VCT.
11/01/2010 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
11/04/2010 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
1) FROM BLDG TO METER LOCATION
2) NEED TO SEE METER AND RPB
01/11/2011 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
01/11/2011 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
01/18/2011 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
01/19/2011 U VALUE FOR WINDOW GDABBS Approved IVRS - Inspection :*
02/02/2011 RIGHT OF WAY - FINAL MCASTRO Approved
02/02/2011 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
02/02/2011 OUTDOOR LIGHTING FINAL RMORENO Approved IVRS - Inspection :*
02/02/2011 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
02/02/2011 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved IVRS - Inspection :*
02/02/2011 ELECTRIC - ABOVE CEILING RMORENO Approved IVRS - Inspection :*
02/02/2011 FIRE - FINAL DSIWARSKI Approved
02/03/2011 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
02/03/2011 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
02/03/2011 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
02/03/2011 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
11/16/2012 NPPO - FINAL DROBERTS Approved
11/16/2012 LANDSCAPE - FINAL DROBERTS Approved
11/16/2012 ENGINEERING - FINAL DROBERTS Approved
12/12/2012 BUILDING - FINAL LHANLY Approved

Documents

File Name Document Type  
C OF O_12-12-2012.TIF CERT OF OCC VIEW
TEMP C OF O_11-04-2010.TIF CERT OF OCC VIEW
001_CS-1.TIF CONSTRPLANS VIEW
002_NOTICE PAGE.TIF CONSTRPLANS VIEW
003_CS-2.TIF CONSTRPLANS VIEW
004_E1.TIF CONSTRPLANS VIEW
005_E2.TIF CONSTRPLANS VIEW
006_E3.TIF CONSTRPLANS VIEW
007_E4.TIF CONSTRPLANS VIEW
008_E5.TIF CONSTRPLANS VIEW
009_E6.TIF CONSTRPLANS VIEW
010_E7.TIF CONSTRPLANS VIEW
011_E8.TIF CONSTRPLANS VIEW
012_E9.TIF CONSTRPLANS VIEW
013_E10.TIF CONSTRPLANS VIEW
014_E11.TIF CONSTRPLANS VIEW
015_F1.TIF CONSTRPLANS VIEW
016_F2.TIF CONSTRPLANS VIEW
017_F2.1.TIF CONSTRPLANS VIEW
018_F3.TIF CONSTRPLANS VIEW
019_F4.TIF CONSTRPLANS VIEW
020_F5.TIF CONSTRPLANS VIEW
021_F6.TIF CONSTRPLANS VIEW
022_F7.TIF CONSTRPLANS VIEW
023_COVER SHEET.TIF CONSTRPLANS VIEW
024_A-1.TIF CONSTRPLANS VIEW
025_A-2.TIF CONSTRPLANS VIEW
026_A-3.TIF CONSTRPLANS VIEW
027_A-4.TIF CONSTRPLANS VIEW
028_A-5.TIF CONSTRPLANS VIEW
029_M-1.TIF CONSTRPLANS VIEW
030_P-1.TIF CONSTRPLANS VIEW
031_P-2.TIF CONSTRPLANS VIEW
032_E-1.TIF CONSTRPLANS VIEW
033_E-2.TIF CONSTRPLANS VIEW
034_C-1.1.TIF CONSTRPLANS VIEW
035_C-1.2.TIF CONSTRPLANS VIEW
036_C-1.3.TIF CONSTRPLANS VIEW
037_C-1.4.TIF CONSTRPLANS VIEW
038_C-1.5.TIF CONSTRPLANS VIEW
039_C-1.6.TIF CONSTRPLANS VIEW
040_C-1.7.TIF CONSTRPLANS VIEW
STRUCCALCS BUILDING 5.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW