Permit: T08CM03746
Permit Details
Apply Date:
11/21/2008
Applicant:
N/A
Description:
RAMADA, PARKING LOT EXPANSION
Architects:
- HUCKO, JOHN RICHARD
Contractors:
- ANDERSON CONSTRUCTION CORP , M
Permit Reviews
Permit Number - T08CM03746
Permit Status: Final
Permit Description: RAMADA, PARKING LOT EXPANSION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/16/2009 | RESUBMITTAL - SITE ALL | 04/08/2009 | COMPLETED |
| 03/16/2009 | RESUBMITTAL | 04/08/2009 | COMPLETED |
| 04/10/2009 | RESUBMITTAL | 06/10/2009 | COMPLETED |
| 04/10/2009 | RESUBMITTAL - SITE | 06/10/2009 | COMPLETED |
| 09/15/2009 | REVISION - - 1ST | 09/15/2009 | COMPLETED |
| 10/16/2009 | REVISION - - 2ND | 10/16/2009 | COMPLETED |
| 11/21/2008 | PLANS OK TO SUBMIT - COMM | 12/22/2008 | COMPLETED |
| 11/21/2008 | PLANS OK TO SUBMIT - SITE | 11/25/2008 | COMPLETED |
| 12/22/2008 | COMMERCIAL NEW | 01/12/2009 | COMPLETED |
| 12/22/2008 | SITE | 01/12/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03746
Permit Status: Final
Permit Description: RAMADA, PARKING LOT EXPANSION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/21/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM03746
Permit Description: RAMADA, PARKING LOT EXPANSION
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2009 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER UNDERGROUND 2) NEED TO SEE CLEANOUTS COMPLETED 3) IF A BACKWATER VALVE IS INSTALLED ON SEWER TO MODULARS, A VENT WILL BE REQUIRED FOR THE SEWER |
| 09/02/2009 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* 1) 4" SDR35 CONNECTED TO 8" OK 2) 4" EXTENDED 17' PAST FIRST UPSTREAM CLEANOUT 3) OK TO COVER AFTER TRACER INSTALLED |
| 11/25/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 11/25/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 11/25/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 11/25/2009 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 12/21/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) LIGHTING, POWER, PANEL AND GROUNDING OK |
| 12/21/2009 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) ABS GROUND CLEANOUT MAY NOT BE EMBEDDED IN CONCRETE. USE CAST IRON COVER OR FRANK PATTERN CLEANOUT COVER FOR CLEANOUT; THEN 18" OF CONCRETE AROUND IT |
| 12/21/2009 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 12/21/2009 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 12/21/2009 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 12/21/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 12/28/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/24/2010 | NPPO - FINAL | ACONNOR | Approved | |
| 02/24/2010 | LANDSCAPE - FINAL | ACONNOR | Approved |