Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
11/19/2008
Applicant:
N/A
Description:
TI: OFFICE, C OF O
Architects:
  • LARRY CLICK
Contractors:
  • DIVERSIFIED DESIGN AND CONSTRUCT

Permit Reviews

Permit Number - T08CM03728
Permit Status: C of o
Permit Description: TI: OFFICE, C OF O
Start Date Submittal Complete Date Status  
11/19/2008 COMMERCIAL TI 01/09/2009 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T08CM03728
Permit Status: C of o
Permit Description: TI: OFFICE, C OF O
Total Outstanding Activity Conditions - 1
Date Name
11/19/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM03728
Permit Description: TI: OFFICE, C OF O
Total Completed Inspections - 21
Date Description Inspector Results Comments
01/15/2009 FRAMING MHENSON Approved IVRS - Inspection :*
01/20/2009 SHEET ROCK NAILING MHENSON Approved IVRS - Inspection :*
01/26/2009 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
01/28/2009 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
01/29/2009 BUILDING ABOVE CEILING MHENSON Approved IVRS - Inspection :*
01/30/2009 PLUMBING - PROGRESS RLEDONNE Approved
01/30/2009 NPPO - FINAL ACONNOR Approved N/A
01/30/2009 LANDSCAPE - FINAL ACONNOR Approved N/A
01/30/2009 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
01/30/2009 FIRE - FINAL LTHOMAS Approved
01/30/2009 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
01/30/2009 TEP CLEARANCE - AM BFLORES Approved TEC PER D.SANTA CRUZ
02/02/2009 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
02/04/2009 BUILDING - PROGRESS MHENSON Approved
02/06/2009 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
02/09/2009 ELECTRIC - FINAL DSANTACR Approved
02/09/2009 ELECTRIC - ABOVE CEILING DSANTACR Approved
02/09/2009 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved
02/09/2009 ELECTRIC - INTERMEDIATE DSANTACR Approved
02/10/2009 ENGINEERING - FINAL MAVERY Approved
02/10/2009 BUILDING - FINAL IVR USER Approved IVRS - AP canceled