Permit: T08CM03566
Permit Details
Apply Date:
11/04/2008
Applicant:
N/A
Description:
TI:SHOW ROOM
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CAMWEST GROUP INC ,
Permit Reviews
Permit Number - T08CM03566
Permit Status: Final
Permit Description: TI:SHOW ROOM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/04/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 11/07/2008 | COMPLETED |
11/07/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 12/03/2008 | COMPLETED |
12/03/2008 | POST 3RD PARTY REVIEW | 12/04/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03566
Permit Status: Final
Permit Description: TI:SHOW ROOM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/04/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM03566
Permit Description: TI:SHOW ROOM
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/08/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
12/11/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK BELOW SLAB CONDUITS & BOXES FOR ELEC. EQUIPT. |
12/16/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* AIR PIPING UNDERGROUND PER PLAN |
12/18/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1. OK TO TAPE UPPER SHEETS IN SHOW ROOM 2. FRAMING DETAIL 9 ON A.4 |
01/08/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CALL BACK FOR CLOSET FLANGE |
01/08/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
01/08/2009 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
01/29/2009 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
01/29/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
02/02/2009 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
02/02/2009 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
02/02/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #101 PER D. SANTACRUZ |
02/11/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
02/11/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
02/11/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
02/11/2009 | SIGN - FINAL | JYBARRA | Approved | |
02/11/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/11/2009 | FIRE - FINAL | LTHOMAS | Approved | |
02/12/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
02/12/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
02/12/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
02/12/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
02/13/2009 | ENGINEERING - FINAL | NKALAHAR | Approved | PER INSP COPY |
02/13/2009 | BUILDING - FINAL | LHANLY | Approved | PER INSP CARD |
02/13/2009 | ENGINEERING - FINAL | NKALAHAR | Approved | RETURNED TO SITE |
02/13/2009 | ENGINEERING - FINAL | NKALAHAR | Approved | SITE NOT READY ROLL OF ON SITE PORTA TOILET ON SITE LOADING ZONE STILL BEING PAINTED WORK STILL CONTINUING |
02/13/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |