Permit: T08CM03471
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3955 E FORT LOWELL RD #04
Address NEW:
3955 E FORT LOWELL RD #04
Apply Date:
10/24/2008
Applicant:
N/A
Description:
TI: NEW MEDICAL OFFICE
Contractors:
- RIO WEST DEVELOPMENT AND CONSTRU
Permit Reviews
Permit Number - T08CM03471
Permit Status: C of o
Permit Description: TI: NEW MEDICAL OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/24/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 10/24/2008 | COMPLETED |
| 10/24/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 12/04/2008 | COMPLETED |
| 12/04/2008 | POST 3RD PARTY REVIEW | 12/08/2008 | COMPLETED |
| 12/08/2008 | RESUBMITTAL | 12/15/2008 | COMPLETED |
| 12/15/2008 | RESUBMITTAL | 12/16/2008 | COMPLETED |
| 12/16/2008 | RESUBMITTAL | 12/19/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03471
Permit Status: C of o
Permit Description: TI: NEW MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/24/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03471
Permit Description: TI: NEW MEDICAL OFFICE
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* 1. WRAP PIPING PASSING THRU CONCRETE POST SUITE # 2. NEED TO SEE SHOWER DRAIN INSTALLATION AND PROPER CONN. TO SHWR PAN |
| 12/24/2008 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) DETAIL #4, PAGE A2 TO BE CHANGED (RFI) TO NOT INCLUDE SLIP TRACK AT TOP TRACK |
| 01/14/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* ENSURE ITEMS #4 & 5 (BELOW) ARE ADDRESSED WHEN MECHANICAL & PLUMBING IN AFFECTED AREAS ARE COMPLETE |
| 01/26/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 02/04/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
| 03/20/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 03/25/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 03/27/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* 1) 106,105,101,102,119,118,117,122,121,116,115,114,113,112,111,110,109,108,107,128 AND 132 CEILING OK |
| 03/30/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR STE. #113, 114 & 115 PER R. MORENO |
| 04/01/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* OK FOR TILES MECHANICAL ONLY |
| 04/23/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 04/23/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 04/30/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* TESTED DUCT SMOKE DETECTORS AIR BALANCE OK OK FOR FINAL |
| 04/30/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 04/30/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 04/30/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 05/01/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | |
| 05/01/2009 | ELECTRIC - PROGRESS | RMORENO | Approved | |
| 05/07/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 05/07/2009 | NPPO - FINAL | PMCLAUGH | Approved | |
| 05/07/2009 | LANDSCAPE - FINAL | PMCLAUGH | Approved | |
| 05/07/2009 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
| 05/07/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 05/07/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 05/07/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 05/07/2009 | SIGN - FINAL | JYBARRA | Approved | OK TO ISSUE PERMANENT C OF O WHEN BOND IS POSTED FOR COMPLETION OF SIGN ON T08OT02586 OR CAN COMPLETE SIGN |