Permit: T08CM03423
Permit Details
Apply Date:
10/20/2008
Applicant:
N/A
Description:
ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Outstanding Activity Conditions
Permit Number - T08CM03423
Permit Status: Final
Permit Description: ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE
R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/20/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM03423
Permit Description: ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE
R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2009 | PLUMBING - SEWER HCS CONNECT | CRUIZ | Approved | IVRS - Inspection :* |
| 01/08/2009 | PLUMBING - ROUGH, SOIL | CRUIZ | Approved | IVRS - Inspection :* |
| 01/12/2009 | BUILDING PRE-SLAB | CRUIZ | Approved | IVRS - Inspection :* |
| 01/12/2009 | EXCAVATION/LAYOUT REBAR & ZON | CRUIZ | Approved | IVRS - Inspection :* |
| 02/12/2009 | REINFORCED MASONRY PRE-GROUT | CRUIZ | Approved | IVRS - Inspection :* |
| 03/04/2009 | ELECTRIC - UNDERGROUND | CRUIZ | Approved | IVRS - Inspection :* |
| 03/10/2009 | ROOF NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 03/20/2009 | ELECTRIC - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 03/31/2009 | PLUMBING - YARD WTR LINE/TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 04/02/2009 | U VALUE FOR WINDOW | CRUIZ | Approved | IVRS - Inspection :* |
| 04/02/2009 | FRAMING | CRUIZ | Approved | IVRS - Inspection :* |
| 04/02/2009 | PLUMBING - GAS PRESSURE TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 04/02/2009 | PLUMBING - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 04/10/2009 | SHEET ROCK NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 06/17/2009 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 06/17/2009 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 06/17/2009 | PLUMBING - GAS PRESS TEST FNL | RCAMACHO | Approved | IVRS - Inspection :* |
| 06/18/2009 | ELECTRIC - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/18/2009 | BUILDING - FINAL | WNORTH | Approved | IVRS - Inspection :* |
| 06/19/2009 | PERMIT FINALED | JWEATHER | Approved |