Permit Details

Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
441 S ELIAS AV
Address NEW:
441 S ELIAS AV
Apply Date:
10/20/2008
Applicant:
N/A
Description:
ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES

Permit Reviews

Permit Number - T08CM03423
Permit Status: Final
Permit Description: ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Start Date Submittal Complete Date Status  
01/06/2009 REVISION - - 1ST 01/06/2009 COMPLETED Review Details
01/16/2009 REVISION - - 2ND 01/16/2009 COMPLETED Review Details
01/20/2009 REVISION - - 3RD 01/20/2009 COMPLETED Review Details
10/20/2008 RESIDENTIAL BLDG/ZONING/ENGINE/WWM 10/20/2008 COMPLETED Review Details
10/20/2008 OTHER 11/24/2008 COMPLETED Review Details
12/01/2008 RESUBMITTAL 12/15/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM03423
Permit Status: Final
Permit Description: ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Total Outstanding Activity Conditions - 1
Date Name
10/20/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T08CM03423
Permit Description: ADDITION: BATHROOM ON EXISTING DETACHED STUDIO SPACE R2: CHANGE TO WINDOW SIZE, CHANGE TO GAS LINES
Total Completed Inspections - 20
Date Description Inspector Results Comments
01/08/2009 PLUMBING - SEWER HCS CONNECT CRUIZ Approved IVRS - Inspection :*
01/08/2009 PLUMBING - ROUGH, SOIL CRUIZ Approved IVRS - Inspection :*
01/12/2009 BUILDING PRE-SLAB CRUIZ Approved IVRS - Inspection :*
01/12/2009 EXCAVATION/LAYOUT REBAR & ZON CRUIZ Approved IVRS - Inspection :*
02/12/2009 REINFORCED MASONRY PRE-GROUT CRUIZ Approved IVRS - Inspection :*
03/04/2009 ELECTRIC - UNDERGROUND CRUIZ Approved IVRS - Inspection :*
03/10/2009 ROOF NAILING CRUIZ Approved IVRS - Inspection :*
03/20/2009 ELECTRIC - INTERMEDIATE CRUIZ Approved IVRS - Inspection :*
03/31/2009 PLUMBING - YARD WTR LINE/TEST CRUIZ Approved IVRS - Inspection :*
04/02/2009 U VALUE FOR WINDOW CRUIZ Approved IVRS - Inspection :*
04/02/2009 FRAMING CRUIZ Approved IVRS - Inspection :*
04/02/2009 PLUMBING - GAS PRESSURE TEST CRUIZ Approved IVRS - Inspection :*
04/02/2009 PLUMBING - INTERMEDIATE CRUIZ Approved IVRS - Inspection :*
04/10/2009 SHEET ROCK NAILING CRUIZ Approved IVRS - Inspection :*
06/17/2009 MECHANICAL - FINAL RCAMACHO Approved IVRS - Inspection :*
06/17/2009 PLUMBING - FINAL RCAMACHO Approved IVRS - Inspection :*
06/17/2009 PLUMBING - GAS PRESS TEST FNL RCAMACHO Approved IVRS - Inspection :*
06/18/2009 ELECTRIC - FINAL WNORTH Approved IVRS - Inspection :*
06/18/2009 BUILDING - FINAL WNORTH Approved IVRS - Inspection :*
06/19/2009 PERMIT FINALED JWEATHER Approved