Permit Number - T08CM03216
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Start Date Submittal Complete Date Status  
01/15/2009 3RD PARTY REVIEW-REVISION/OTHER 01/21/2009 COMPLETED Review Details
02/11/2009 REVISION - - 1ST 02/18/2009 COMPLETED Review Details
02/18/2009 REVISION - - 1ST 02/18/2009 COMPLETED Review Details
03/23/2009 REVISION - - 2ND 03/23/2009 COMPLETED Review Details
09/29/2008 PLANS OK TO SUBMIT - 3RD PARTY 09/30/2008 COMPLETED Review Details
09/30/2008 3RD PARTY REVIEW-COMMERCIAL 11/17/2008 COMPLETED Review Details
11/17/2008 POST 3RD PARTY REVIEW 11/26/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM03216
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Total Outstanding Activity Conditions - 1
Date Name
09/29/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM03216
Permit Description: NEW MEDICAL BUILDING
Total Completed Inspections - 35
Date Description Inspector Results Comments
12/23/2008 PLUMBING - SEWER HCS CONNECT BBENEDON Approved
12/23/2008 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/24/2008 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
1. INSTALLED PER PLAN OK TO COVER
2. IPC ALLOWED ONLY IF APPROVED
BY CITY OF TUCSON BUILDING OFFICIAL
3. REVISE COVER PAGE TS1 AND P-1 OR PROVIDE SIGNED PETITION OF APPEAL
12/30/2008 ELECTRIC - UNDERGROUND RMORENO Approved IVRS - Inspection :*
1) NORTH EAST CORNER SERVICE TO MIDWAY 2 1/2, 1 1/2 PHONE FROM MIDWAY TO SERVICE NORTH EAST CORNER
01/08/2009 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
OK 1 # 1/0 CU BOND
01/08/2009 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
OK TO POUR
01/08/2009 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
CONTINUOUS FOOTINGS (F1); COLUMNS C1/F3, C2/F4
SHEAR WALL (F-4) (F-5) -- OK TO POUR PROGRESS AREAS
01/30/2009 ROOF NAILING JBURGE Approved IVRS - Inspection :*
CRICKETS, TOWERS & SCUPPERS ARE COMPLETE
OK TO COVER ROOF SYSTEM
01/30/2009 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
OK TO STUCCO MESH EXTERIOR WALLS
02/18/2009 FRAMING JBURGE Approved IVRS - Inspection :*
OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING
INTERMEDIATES
02/26/2009 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
OK TO TAPE THROUGHOUT
03/11/2009 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
SHADE PIPING W/CLEAN FILL PRIOR TO BACKFILLING W/CHUNKY DIRT AND ROCKS

ATTACH TRACER WIRE TO PEX EVERY 8' O.C. PER STATE LAW
USE NOT TAPE
03/24/2009 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
OK TO SET CEILING TILES
03/24/2009 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
04/06/2009 ELECTRIC - PROGRESS RMORENO Approved IVRS - Inspection :*
04/07/2009 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED PER R. MORENO
04/08/2009 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
CLOSET FLANGES OK
04/09/2009 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
04/17/2009 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
AIR BALANCE OK
04/17/2009 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
04/17/2009 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
04/17/2009 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
04/17/2009 NPPO - FINAL ACONNOR Approved
04/17/2009 LANDSCAPE - FINAL ACONNOR Approved
04/17/2009 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
04/17/2009 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved IVRS - Inspection :*
04/17/2009 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
04/17/2009 FIRE - FINAL LTHOMAS Approved
04/17/2009 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
04/21/2009 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
04/21/2009 STUCCO MESH JBURGE Approved IVRS - Inspection :*
04/21/2009 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
04/22/2009 ENGINEERING - FINAL JBRUCKME Approved
04/27/2009 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
05/01/2009 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*