Permit: T08CM03216
Permit Details
Apply Date:
09/29/2008
Applicant:
N/A
Description:
NEW MEDICAL BUILDING
Contractors:
- VENTURE WEST INC *C
Permit Reviews
Permit Number - T08CM03216
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/15/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 01/21/2009 | COMPLETED |
02/11/2009 | REVISION - - 1ST | 02/18/2009 | COMPLETED |
02/18/2009 | REVISION - - 1ST | 02/18/2009 | COMPLETED |
03/23/2009 | REVISION - - 2ND | 03/23/2009 | COMPLETED |
09/29/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 09/30/2008 | COMPLETED |
09/30/2008 | 3RD PARTY REVIEW-COMMERCIAL | 11/17/2008 | COMPLETED |
11/17/2008 | POST 3RD PARTY REVIEW | 11/26/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03216
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/29/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03216
Permit Description: NEW MEDICAL BUILDING
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2008 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | |
12/23/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
12/24/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* 1. INSTALLED PER PLAN OK TO COVER 2. IPC ALLOWED ONLY IF APPROVED BY CITY OF TUCSON BUILDING OFFICIAL 3. REVISE COVER PAGE TS1 AND P-1 OR PROVIDE SIGNED PETITION OF APPEAL |
12/30/2008 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) NORTH EAST CORNER SERVICE TO MIDWAY 2 1/2, 1 1/2 PHONE FROM MIDWAY TO SERVICE NORTH EAST CORNER |
01/08/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* OK 1 # 1/0 CU BOND |
01/08/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR |
01/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CONTINUOUS FOOTINGS (F1); COLUMNS C1/F3, C2/F4 SHEAR WALL (F-4) (F-5) -- OK TO POUR PROGRESS AREAS |
01/30/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* CRICKETS, TOWERS & SCUPPERS ARE COMPLETE OK TO COVER ROOF SYSTEM |
01/30/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO MESH EXTERIOR WALLS |
02/18/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
02/26/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
03/11/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* SHADE PIPING W/CLEAN FILL PRIOR TO BACKFILLING W/CHUNKY DIRT AND ROCKS ATTACH TRACER WIRE TO PEX EVERY 8' O.C. PER STATE LAW USE NOT TAPE |
03/24/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO SET CEILING TILES |
03/24/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
04/06/2009 | ELECTRIC - PROGRESS | RMORENO | Approved | IVRS - Inspection :* |
04/07/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. MORENO |
04/08/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
04/09/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* AIR BALANCE OK |
04/17/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | NPPO - FINAL | ACONNOR | Approved | |
04/17/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/17/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
04/17/2009 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
04/17/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
04/17/2009 | FIRE - FINAL | LTHOMAS | Approved | |
04/17/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
04/21/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
04/21/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
04/21/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
04/22/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
04/27/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
05/01/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |