Permit: T08CM03168
Permit Details
Apply Date:
09/23/2008
Applicant:
N/A
Description:
REMODEL:RESIDENTIAL UNITS
Architects:
- TOM, RICHARD FE
Contractors:
- TOFEL CONSTRUCTION
Permit Reviews
Permit Number - T08CM03168
Permit Status: C of o
Permit Description: REMODEL:RESIDENTIAL UNITS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/01/2009 | REVISION - - 1ST | 09/01/2009 | COMPLETED |
09/23/2008 | PLANS OK TO SUBMIT - COMM | 09/30/2008 | COMPLETED |
09/30/2008 | COMMERCIAL TI | 11/03/2008 | COMPLETED |
12/05/2008 | RESUBMITTAL | 01/05/2009 | COMPLETED |
12/22/2008 | RESUBMITTAL | 09/01/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03168
Permit Status: C of o
Permit Description: REMODEL:RESIDENTIAL UNITS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/23/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03168
Permit Description: REMODEL:RESIDENTIAL UNITS
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) PVC UNDERSLAB OK TO COVER |
09/28/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* 1) ALL INTERIOR SLABS ARE COMPLETE |
10/13/2009 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* 1) AT RESTROOM ONLY |
10/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* 1) STAIRWAY FOOTER |
10/13/2009 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
10/15/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* 1) PLEASE HAVE ENGINEER OF RECORD TO ADDRESS FEEDER SIZES AND CONDUCTOR MATERIAL 2) COURTESY INSPECTION, NO WORK DONE YET |
10/27/2009 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
11/03/2009 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) OK WALLS/HARD LIDS ALL UNITS THIS BLDG 2) SER CABLES NOT TERMINATED YET |
11/05/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | 1) FAN COILS WILL REQUIRE A DISCONNECTING MEANS WITHIN SIGHT OF THE FAN COIL |
11/06/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* 1) SOFFITS ONLY |
11/09/2009 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) CHECK 1ST FLOOR FLANGES-TO BE SECURE TO THE FLOOR, 2ND AND 3RD FLOORS NOT READY |
11/13/2009 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/25/2009 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* 1) ALL 8 UNITS FIRE CAULKING FOR COND. AND REFRIG. LINES AT INTERIOR AIR HANDLER |
12/18/2009 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER ALL AREAS |
01/08/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
01/08/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
01/08/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
01/08/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
01/21/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
02/05/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK |
02/11/2010 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
02/11/2010 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
02/11/2010 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
02/11/2010 | FIRE - FINAL | DRamirez | Approved | Approved 2/11/10. |
02/11/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
02/11/2010 | NPPO - FINAL | ACONNOR | Approved | |
02/11/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | |
02/16/2010 | ELECTRIC - UFER | DSANTACR | Approved | |
02/16/2010 | FIRE - ALARM FINAL | DRAMIREZ | Approved | |
02/16/2010 | FIRE SPKLR - FINAL | DRAMIREZ | Approved | |
02/16/2010 | FIRE SPKLR - UG, PIPING, HYDRO | DRAMIREZ | Approved | |
02/17/2010 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
02/17/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |