Permit: T08CM02986
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
9012 S CEDARBROOK LN
Address NEW:
9012 S CEDARBROOK LN
Apply Date:
09/03/2008
Applicant:
RICHMOND AMERICAN HOMES *C
Description:
SFR RICH379-07 T07-M0128
Contractors:
- RICHMOND AMERICAN HOMES *C
Permit Reviews
Permit Number - T08CM02986
Permit Status: C of o
Permit Description: SFR RICH379-07 T07-M0128
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/03/2008 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 09/05/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02986
Permit Status: C of o
Permit Description: SFR RICH379-07 T07-M0128
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/03/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02986
Permit Description: SFR RICH379-07 T07-M0128
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2008 | PLUMBING - SEWER HCS CONNECT | WNORTH | Approved | IVRS - Inspection :* |
| 09/15/2008 | PLUMBING - YARD WTR LINE/TEST | WNORTH | Approved | IVRS - Inspection :* |
| 09/15/2008 | PLUMBING - ROUGH, SOIL | WNORTH | Approved | IVRS - Inspection :* |
| 09/18/2008 | ELECTRIC - UNDERGROUND | RFREIDIN | Approved | IVRS - Inspection :* |
| 09/18/2008 | ELECTRIC - UFER | RFREIDIN | Approved | IVRS - Inspection :* |
| 09/18/2008 | BUILDING PRE-SLAB | RFREIDIN | Approved | IVRS - Inspection :* |
| 09/18/2008 | EXCAVATION/LAYOUT REBAR & ZON | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/07/2008 | ROOF NAILING | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/09/2008 | EXT METAL CLIPS/EXT SHEATHING | RFREIDIN | Approved | IVRS - Inspection :* 1) OK TO COVER EXT. BEFORE LOADING ROOF 2) CHECK FOR TRUSS A02, INSTALLED END FOR END 4 PT BEARING |
| 10/16/2008 | PLUMBING - GAS PRESSURE TEST | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/16/2008 | PLUMBING - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/16/2008 | ELECTRIC - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/16/2008 | U VALUE FOR WINDOW | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/16/2008 | STUCCO MESH | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/20/2008 | MECHANICAL - INTERMEDIATE | RFREIDIN | Approved | IVRS - Inspection :* |
| 10/20/2008 | FRAMING | RFREIDIN | Approved | IVRS - Inspection :* |
| 11/03/2008 | ELECTRIC - TEMPORARY SERVICE | WNORTH | Approved | IVRS - Inspection :* |
| 11/03/2008 | ELECTRIC - CABLE DROP | WNORTH | Approved | IVRS - Inspection :* |
| 11/03/2008 | SHEET ROCK NAILING | WNORTH | Approved | IVRS - Inspection :* |
| 11/04/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER W. NORTH |
| 11/13/2008 | ASSURANCE | MCARREON | Approved | |
| 01/15/2009 | MECHANICAL - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 01/15/2009 | PLUMBING - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 01/15/2009 | ELECTRIC - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 01/15/2009 | BUILDING - FINAL | RFREIDIN | Approved | IVRS - Inspection :* |
| 01/16/2009 | PERMIT FINALED | JWEATHER | Approved |