Permit: T08CM02969
Permit Details
Apply Date:
09/03/2008
Applicant:
N/A
Description:
TI:MANUFACTURING
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T08CM02969
Permit Status: C of o
Permit Description: TI:MANUFACTURING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/03/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 09/03/2008 | COMPLETED |
| 09/03/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 10/15/2008 | COMPLETED |
| 09/03/2008 | POST 3RD PARTY REVIEW | 10/16/2008 | COMPLETED |
| 12/10/2008 | REVISION - - 1ST | 12/10/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02969
Permit Status: C of o
Permit Description: TI:MANUFACTURING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/03/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02969
Permit Description: TI:MANUFACTURING
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/17/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/22/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/03/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 11/17/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* RESTROOM CEILINGS & HALLWAY CEILING -- OK TO TAPE |
| 12/02/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/02/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/03/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/03/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/03/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 12/03/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 12/04/2008 | TEP CLEARANCE - AM | BFLORES | Approved | TEC PER D.SANTA CRUZ |
| 12/05/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 12/05/2008 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 12/05/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 12/08/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 12/11/2008 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* |
| 12/11/2008 | ENGINEERING - FINAL | MAVERY | Approved | |
| 12/11/2008 | SIGN - FINAL | JYBARRA | Approved | |
| 12/11/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/12/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* CLEAN WATER REPORT ON SITE |
| 12/15/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
| 12/15/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 12/16/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
| 12/16/2008 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 12/16/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 12/17/2008 | PERMIT FINALED | LJACKSON | Approved |