Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Withdrwn
Type:
COMMERCIAL ADDITION
Apply Date:
08/18/2008
Applicant:
N/A
Description:
ADDITION: WAREHOUSE

Permit Reviews

Permit Number - T08CM02814
Permit Status: Withdrwn
Permit Description: ADDITION: WAREHOUSE
Start Date Submittal Complete Date Status  
08/18/2008 PLANS OK TO SUBMIT - COMM 09/05/2008 COMPLETED Review Details
09/05/2008 3RD PARTY REVIEW-COMMERCIAL 10/07/2008 COMPLETED Review Details
10/07/2008 POST 3RD PARTY REVIEW 11/04/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM02814
Permit Status: Withdrwn
Permit Description: ADDITION: WAREHOUSE
Total Outstanding Activity Conditions - 10
Date Name
08/18/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/07/2008 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/07/2008 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
10/07/2008 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/07/2008 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/07/2008 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/07/2008 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/07/2008 SPECIAL INSPECTION IS REQUIRED FOR SITE PREP PER U.A.C. SECTION 306.
10/07/2008 SPECIAL INSPECTION IS REQUIRED FOR EXCAVATION PER U.A.C. SECTION 306.
10/07/2008 SPECIAL INSPECTION IS REQUIRED FOR REINFORCED CONCRETE PER U.A.C. SECTION 306.

Outstanding Inspections

Permit Status: Withdrwn
Permit Number: T08CM02814
Permite Description: ADDITION: WAREHOUSE
Total Outstanding Inspections - 26
Last Inspection Date Description Inspector Results Comments
EXCAVATION/LAYOUT REBAR & ZON N/A Not Inspected
STEM WALL/RETAINING WALL N/A Not Inspected
BUILDING PRE-SLAB N/A Not Inspected
REINFORCED MASONRY PRE-GROUT N/A Not Inspected
EXT METAL CLIPS/EXT SHEATHING N/A Not Inspected
ROOF NAILING N/A Not Inspected
FRAMING N/A Not Inspected
BUILDING - PROGRESS N/A Not Inspected
BUILDING - FINAL N/A Not Inspected
ELECTRIC - UFER N/A Not Inspected
ELECTRIC - UNDERGROUND N/A Not Inspected
ELECTRIC - INTERMEDIATE N/A Not Inspected
ELECTRIC - SERVICE RELOCATION N/A Not Inspected
ELECTRIC - TEMPORARY SERVICE N/A Not Inspected
ELECTRIC - CONSTRUCTION POWER N/A Not Inspected
ELECTRIC - RECONNECT N/A Not Inspected
ELECTRIC - PROGRESS N/A Not Inspected
ELECTRIC - FINAL N/A Not Inspected
PLUMBING - ROUGH, SOIL N/A Not Inspected
PLUMBING - INTERMEDIATE N/A Not Inspected
PLUMBING - ABOVE CEILING N/A Not Inspected
PLUMBING - ROOF DRAINS N/A Not Inspected
PLUMBING - SEWER HCS CONNECT N/A Not Inspected
PLUMBING - PROGRESS N/A Not Inspected
PLUMBING - FINAL N/A Not Inspected
FIRE SPKLR - FINAL N/A Not Inspected