Permit: T08CM02657
Permit Details
Apply Date:
08/01/2008
Applicant:
N/A
Description:
NEW: MIDDLE SCHOOL (CLASSROOMS) BUILDING 4
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T08CM02657
Permit Status: C of o
Permit Description: NEW: MIDDLE SCHOOL (CLASSROOMS) BUILDING 4
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/14/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 01/15/2009 | COMPLETED |
05/07/2009 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 05/08/2009 | COMPLETED |
08/01/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 08/01/2008 | COMPLETED |
08/01/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/17/2008 | COMPLETED |
09/17/2008 | POST 3RD PARTY REVIEW | 09/19/2008 | COMPLETED |
09/19/2008 | POST 3RD PARTY REVIEW | 10/01/2008 | COMPLETED |
10/01/2008 | POST 3RD PARTY REVIEW | 10/06/2008 | COMPLETED |
12/18/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 12/22/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02657
Permit Status: C of o
Permit Description: NEW: MIDDLE SCHOOL (CLASSROOMS) BUILDING 4
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/01/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02657
Permit Description: NEW: MIDDLE SCHOOL (CLASSROOMS) BUILDING 4
Total Completed Inspections - 43
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/20/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* CONTINUOUS BLDG. FOOTING @ GRID LINES 4.0 NORTH/A.1 SOUTH OK |
10/20/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
10/28/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 2 1/2 T/K STUB UP & OUT OF BLD. OK |
10/31/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST THRU BLD. TO INITIAL PAGE 4 P1.1 OK |
11/07/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* OK U.G FOR BRANCH CIRCUITS & FEEDERS UNDER BUILDING SLAB |
11/10/2008 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* RETAINING WALL @ SW SIDE OF BLDG. #4 DETAIL #52 PG. S1.5 OK TO POUR FOOTING |
11/13/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
11/13/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
12/30/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) OK TOP OF WALL EAST COURTYARD ENTRANCE |
12/30/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* 1) CMU WALL REINFORCEMENT STEEL AT GRID EAST WALLS OF ROOMS #419 & 420 FROM 0'-4' AND EAST WALLS OF ROOMS #419 & 420 FROM 4' TO 8' AFFE SPECIAL INSPECTION PERFORMED |
01/20/2009 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* BLDG. #4 OK TO DRY IN |
01/28/2009 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
01/30/2009 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
03/02/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
04/01/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
04/01/2009 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
04/02/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
04/02/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
04/07/2009 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* T&P TO TERMINATE AT 90 DEG. DOWN |
04/07/2009 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
04/15/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
05/12/2009 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
05/14/2009 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
05/29/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* STERILIZATION AND BACTERIA REPORT OK |
05/29/2009 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
06/03/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL 2) DUCT SMOKE DETCTOR TEST OK 3) AIR BALANCE OK |
06/03/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
06/29/2009 | BUILDING - PROGRESS | GDABBS | Approved | |
06/29/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
06/29/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
06/29/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
06/30/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
06/30/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
06/30/2009 | FIRE - LANE SIGNS | LTHOMAS | Approved | |
06/30/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
06/30/2009 | FIRE - FINAL | LTHOMAS | Approved | |
06/30/2009 | ENGINEERING - FINAL | JFEMLING | Approved | Approved for C of O, call for final grading inspection |
07/01/2009 | PERMIT FINALED | JWEATHER | Approved | |
07/01/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |